815 W 110TH ST 90044
Certificate Information: 815 W 110TH ST 90044
- Application / Permit
- 23010-10000-03525
- Plan Check / Job No.
- B23LA16372
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Convert Dettached Garage at rear of the lot to An Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/5/2023
- Issuing Office
- Current Status
- CofO in Progress on 6/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2023 | EDWIN ESPIN |
| Corrections Issued | 9/10/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 10/17/2023 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/13/2023 | DAVID CASTILLO |
| Plan Check Approved | 12/3/2023 | AMY GUEVARRA |
| Issued | 12/5/2023 | APPLICANT |
| CofO in Progress | 6/4/2026 | ARTHUR NEGRETE |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 9/30/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abdel, Messih, Raymond; Lic. No.: C79913 | 23216 CICELY CT VALENCIA, CA 91354 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/10/2025 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/29/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 1/31/2025 | Corrections Issued | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 2/4/2025 | Conditional Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 2/4/2025 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Rough | 2/4/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 2/12/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 2/12/2025 | Partial Approval | BEN MOLSTAD |
| Deputy Drilled-In Anchors | 2/14/2025 | Conditional Approval | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 4/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/4/2025 | Corrections Issued | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/4/2025 | Corrections Issued | BEN MOLSTAD |
| Wood Frame | 4/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/8/2025 | Partial Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 4/8/2025 | Not Ready for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 4/10/2025 | Corrections Issued | BEN MOLSTAD |
| Insulation | 4/10/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/10/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/14/2025 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/17/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 4/18/2025 | Approved | BEN MOLSTAD |
| Insulation | 4/21/2025 | Corrections Issued | BEN MOLSTAD |
| Drywall Nailing | 5/9/2025 | Corrections Issued | BEN MOLSTAD |
| Drywall Nailing | 6/6/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 6/6/2025 | Corrections Issued | BEN MOLSTAD |
| Insulation | 6/30/2025 | Corrections Issued | JOSEPH MCGARRY |
| Final | 8/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 8/7/2025 | Approved | BEN MOLSTAD |
| Insulation | 8/7/2025 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 8/7/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 8/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 8/15/2025 | Corrections Issued | BEN MOLSTAD |
| Insulation | 8/20/2025 | Approved | BEN MOLSTAD |
| Drywall Nailing | 8/22/2025 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/22/2025 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/12/2026 | Corrections Issued | BEN MOLSTAD |
| Final | 3/12/2026 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 3/12/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 3/12/2026 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 5/4/2026 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 6/3/2026 | Approved | ARTHUR NEGRETE |
| Final | 6/3/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| HVAC-Final | 6/3/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 6/3/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 6/3/2026 | Approved | ARTHUR NEGRETE |