3432 E EAGLE ST 90063

Certificate Information: 3432 E EAGLE ST 90063

Application / Permit
23010-10000-03465
Plan Check / Job No.
B22LA27057
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERSION AND MAJOR REMODEL OF (E) (360 SQFT) 2-CAR GARAGE AT REAR OF LOT TO 1 STORY ADU PER LAMC 12.22 A.33(c)-(d) WITH (70.5 SQFT) ADDITION TO BECOME A TOTAL OF 430.5 SQFT ADU WITH ROOF DECK DEMO 99% OF (E) GARAGE AND KEEP 1' OF WALL WITH FOOTING.
Permit Issued
Issued on 4/8/2024
Issuing Office
Current Status
CofO Issued on 10/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 JAD BASMA
Corrections Issued 9/22/2023 JAD BASMA
Quality Review Completed 10/2/2023 GARO TELMI
Applicant returned to address corrections 11/30/2023 JAD BASMA
Plan Check Approved 12/7/2023 JAD BASMA
Issued 4/8/2024 APPLICANT
CofO in Progress 9/7/2025 FREDDIE RIVERA
No Progress 9/13/2025 DEROLD HAUFF
CofO in Progress 9/13/2025 DEROLD HAUFF
Permit Finaled 10/9/2025 DEROLD HAUFF
Permit Finaled 10/9/2025 DEROLD HAUFF
CofO Issued 10/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Clean Up Green Up Cleared 9/26/2023 RUBEN VASQUEZ
Address approval Cleared 9/30/2023 STEVE MELGAR
Roof/Waste drainage to street Cleared 9/30/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/11/2023 STEVE MELGAR
Sewer availability Cleared 10/11/2023 STEVE MELGAR
Public Works-Highway Ded. Cleared 10/11/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 6/5/2024 Partial Approval FREDDIE RIVERA
Deputy Drilled-In Anchors 6/25/2024 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/26/2024 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 10/18/2024 Approved JOHN QUINTANILLA
Underground Mechanical 2/20/2025 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 3/20/2025 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 3/26/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/7/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 4/7/2025 Approved FREDDIE RIVERA
Green Building Rough 4/7/2025 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 4/7/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/15/2025 Partial Approval ARTHUR NEGRETE
Green Building Rough 4/15/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 4/17/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 4/29/2025 Conditional Approval FREDDIE RIVERA
Insulation 4/29/2025 Approved FREDDIE RIVERA
Drywall Nailing 5/13/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/13/2025 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 6/24/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/15/2025 Approved FREDDIE RIVERA
Final 8/15/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 8/15/2025 Partial Inspection FREDDIE RIVERA
MERV13>=Final 8/15/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 8/15/2025 Approved FREDDIE RIVERA
Final 8/20/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 8/20/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/20/2025 SGSOV Approved FREDDIE RIVERA
Final 9/8/2025 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 9/18/2025 Approved FREDDIE RIVERA