4055-4055 1/2 E BEMIS ST 90039

Certificate Information: 4055-4055 1/2 E BEMIS ST 90039

Application / Permit
23010-10000-03438
Plan Check / Job No.
B23LA16015
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan CONVERSION OF (E) GARAGE WITH ADDITION TO BECOME 1-STORY 775 SQFT ACCESSORY DWELLING UNIT (PER LAMC12.22A.33 c,d) WITH ATTACHED OUTDOOR LAUNDRY ROOM AND ATTACHED NEW 1-STORY 789 SQFT SFD PER SB9 LAW (per SB9 Two-Unit Development Ca Govt Code 65852.21) WITH OUTDOOR STORAGE AND ATTACHED COVERED PATIO NEW ROOF TOP DECK OVER PROPOSED ADU AND SFD PER SB9 LAW NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 5/20/2024
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 JAD BASMA
Corrections Issued 9/21/2023 JAD BASMA
Quality Review Completed 10/2/2023 GARO TELMI
Applicant returned to address corrections 12/21/2023 JAD BASMA
Applicant returned to address corrections 3/29/2024 JAD BASMA
Plan Check Approved 4/24/2024 JAD BASMA
No Progress 5/3/2024 JAD BASMA
Plan Check Approved 5/3/2024 JAD BASMA
Issued 5/20/2024 APPLICANT
CofO in Progress 3/31/2026 NICHOLAS LOPEZ
Permit Finaled 4/2/2026 DEROLD HAUFF
CofO Issued 4/2/2026 DEROLD HAUFF
Permit Finaled 4/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/26/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/31/2023 JEANIE LAM
Sewer availability Cleared 10/31/2023 JEANIE LAM
Low Impact Development (LID) Cleared 11/14/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/15/2023 JEANIE LAM
Hydrant and Access approval Cleared 12/1/2023 JOHN CONNEALLY
Senate Bill 9 Cleared 4/2/2024 SPENCER WEJROWSKI
ZI Cleared 4/2/2024 SPENCER WEJROWSKI

Contact Information

Contractor S - Ac Builders; Lic. No.: 1116412-B       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/7/2024 Partial Inspection THOMAS LOGRASSO
PLUMBING-Rough 7/25/2024 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 10/15/2024 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 10/18/2024 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 10/24/2024 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 10/25/2024 Approved THOMAS LOGRASSO
PLUMBING-Rough 12/20/2024 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 1/3/2025 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 1/7/2025 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 1/27/2025 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 1/27/2025 Corrections Issued THOMAS LOGRASSO
Special/Order Compliance 1/27/2025 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 3/13/2025 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Rough 3/13/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Rough 3/13/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 3/13/2025 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 3/26/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 3/26/2025 Approved NICHOLAS LOPEZ
Green Building Rough 3/26/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 3/26/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 4/8/2025 Partial Approval ALEX COLIN
Insulation 4/11/2025 Corrections Issued NICHOLAS LOPEZ
Sewer 4/22/2025 Approved NICHOLAS LOPEZ
Gas Test 4/24/2025 Approved LILIANA PORTILLO
Insulation 4/24/2025 Corrections Issued LILIANA PORTILLO
Drywall Nailing 5/1/2025 Approved REGINA MENDEZ
Insulation 5/1/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 5/1/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/10/2025 Approved NICHOLAS LOPEZ
Shower Pan 6/10/2025 Not Ready for Inspection NICHOLAS LOPEZ
Interior/Exterior Lathing 6/16/2025 Not Ready for Inspection NICHOLAS LOPEZ
Shower Pan 6/16/2025 Not Ready for Inspection NICHOLAS LOPEZ
Interior/Exterior Lathing 6/26/2025 Approved REGINA MENDEZ
Shower Pan 6/26/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 7/18/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 7/18/2025 Approved NICHOLAS LOPEZ
Green Building Rough 7/18/2025 Approved NICHOLAS LOPEZ
Pre-Inspection 8/25/2025 Partial Inspection NICHOLAS LOPEZ
Service/Power Release 8/25/2025 Corrections Issued NICHOLAS LOPEZ
Pre-Inspection 9/5/2025 Partial Inspection NICHOLAS LOPEZ
Pre-Inspection 12/3/2025 Partial Inspection NICHOLAS LOPEZ
ELECTRICAL-Final 1/22/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 1/22/2026 Approved NICHOLAS LOPEZ
Service/Power Release 1/22/2026 Not Ready for Inspection NICHOLAS LOPEZ
Final 2/6/2026 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 2/6/2026 Approved NICHOLAS LOPEZ
Green Building Final 2/6/2026 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 2/6/2026 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 2/6/2026 Corrections Issued NICHOLAS LOPEZ
Final 2/13/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 2/13/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/13/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 2/13/2026 Approved NICHOLAS LOPEZ
Final 3/10/2026 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Not Ready NICHOLAS LOPEZ
Final 3/12/2026 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Approved NICHOLAS LOPEZ
Final 3/27/2026 OK to Issue CofO NICHOLAS LOPEZ
Service/Power Release 3/27/2026 Not Required NICHOLAS LOPEZ