4786 E TEMPLETON ST 90032

Certificate Information: 4786 E TEMPLETON ST 90032

Application / Permit
23010-10000-03411
Plan Check / Job No.
B23LA15853
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN PROPOSED DETACHED ADU PER STATE CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/2/2024
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2023 APPLICANT
Assigned to Plan Check Engineer 8/30/2023 NEHEMIAS RAMOS
Corrections Issued 8/31/2023 NEHEMIAS RAMOS
Applicant returned to address corrections 12/15/2023 SUNMIN LEE
Applicant returned to address corrections 1/10/2024 MICHAEL LOPEZ
Plan Check Approved 1/21/2024 MICHAEL LOPEZ
Issued 2/2/2024 APPLICANT
CofO in Progress 7/5/2024 LILIANA PORTILLO
Permit Finaled 7/9/2024 DEROLD HAUFF
CofO Issued 7/9/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/5/2023 ROBERT HUGHES
Address approval Cleared 9/9/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 9/9/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/14/2023 CELINA MORENO
Sewer availability Cleared 9/14/2023 CELINA MORENO
"D" conditions Cleared 10/10/2023 JASON CHAN
"Q" conditions Cleared 10/10/2023 JASON CHAN
Construction near power lines Cleared 12/12/2023 RIDWAN HARDY
ZI Cleared 1/11/2024 JASON CHAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B 21204 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/29/2024 Corrections Issued LILIANA PORTILLO
Pre-Inspection 3/1/2024 Partial Inspection LILIANA PORTILLO
Footing/Foundation/Slab 3/14/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 3/26/2024 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 3/26/2024 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 3/26/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 3/27/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 4/12/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Approved LILIANA PORTILLO
HVAC-Rough 4/12/2024 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 4/12/2024 Corrections Issued LILIANA PORTILLO
Underground Mechanical 4/12/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 4/18/2024 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 5/6/2024 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 5/6/2024 Approved LILIANA PORTILLO
HVAC-Rough 5/6/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 5/6/2024 Approved LILIANA PORTILLO
HVAC-Rough 5/8/2024 Approved LILIANA PORTILLO
Insulation 5/8/2024 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 5/8/2024 Partial Approval LILIANA PORTILLO
Insulation 5/10/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/16/2024 Approved LILIANA PORTILLO
Shower Pan 5/16/2024 Approved LILIANA PORTILLO
Sewer 6/4/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/24/2024 Approved LILIANA PORTILLO
Final 6/24/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 6/24/2024 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 6/24/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/24/2024 SGSOV Not Required LILIANA PORTILLO
Service/Power Release 6/24/2024 Not Required LILIANA PORTILLO
Smoke Detectors 6/24/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 7/3/2024 Approved LILIANA PORTILLO
Final 7/3/2024 OK to Issue CofO LILIANA PORTILLO
Green Building Final 7/3/2024 Approved LILIANA PORTILLO
HVAC-Final 7/3/2024 Approved LILIANA PORTILLO
PLUMBING-Final 7/3/2024 Approved LILIANA PORTILLO