4786 E TEMPLETON ST 90032
Certificate Information: 4786 E TEMPLETON ST 90032
- Application / Permit
- 23010-10000-03411
- Plan Check / Job No.
- B23LA15853
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN PROPOSED DETACHED ADU PER STATE CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/2/2024
- Issuing Office
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2023 | NEHEMIAS RAMOS |
| Corrections Issued | 8/31/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 12/15/2023 | SUNMIN LEE |
| Applicant returned to address corrections | 1/10/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 1/21/2024 | MICHAEL LOPEZ |
| Issued | 2/2/2024 | APPLICANT |
| CofO in Progress | 7/5/2024 | LILIANA PORTILLO |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
| CofO Issued | 7/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/5/2023 | ROBERT HUGHES |
| Address approval | Cleared | 9/9/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/9/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2023 | CELINA MORENO |
| Sewer availability | Cleared | 9/14/2023 | CELINA MORENO |
| "D" conditions | Cleared | 10/10/2023 | JASON CHAN |
| "Q" conditions | Cleared | 10/10/2023 | JASON CHAN |
| Construction near power lines | Cleared | 12/12/2023 | RIDWAN HARDY |
| ZI | Cleared | 1/11/2024 | JASON CHAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/29/2024 | Corrections Issued | LILIANA PORTILLO |
| Pre-Inspection | 3/1/2024 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/14/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/26/2024 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 3/26/2024 | Partial Approval | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 3/26/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 3/27/2024 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/12/2024 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 4/12/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 4/12/2024 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 4/12/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/18/2024 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/6/2024 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/6/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/6/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 5/6/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/8/2024 | Approved | LILIANA PORTILLO |
| Insulation | 5/8/2024 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/8/2024 | Partial Approval | LILIANA PORTILLO |
| Insulation | 5/10/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 5/16/2024 | Approved | LILIANA PORTILLO |
| Shower Pan | 5/16/2024 | Approved | LILIANA PORTILLO |
| Sewer | 6/4/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/24/2024 | Approved | LILIANA PORTILLO |
| Final | 6/24/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 6/24/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 6/24/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 6/24/2024 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 6/24/2024 | Not Required | LILIANA PORTILLO |
| Smoke Detectors | 6/24/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/3/2024 | Approved | LILIANA PORTILLO |
| Final | 7/3/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 7/3/2024 | Approved | LILIANA PORTILLO |
| HVAC-Final | 7/3/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/3/2024 | Approved | LILIANA PORTILLO |