4831 N MURIETTA AVE 91423
Certificate Information: 4831 N MURIETTA AVE 91423
- Application / Permit
- 23010-10000-03408
- Plan Check / Job No.
- B23LA15850
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SFD WITH ATTACHED GARAGE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS (2-STORY)
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | CARLOS MONTES |
| Corrections Issued | 9/5/2023 | CARLOS MONTES |
| Quality Review Completed | 9/6/2023 | GARO TELMI |
| Applicant returned to address corrections | 2/20/2024 | CARLOS MONTES |
| Plan Check Approved | 3/5/2024 | CARLOS MONTES |
| Plan Check Approved | 3/14/2024 | CARLOS MONTES |
| No Progress | 3/14/2024 | CARLOS MONTES |
| Plan Check Approved | 3/14/2024 | CARLOS MONTES |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 2/4/2025 | MISAEL ESPARZA |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
| CofO Issued | 4/3/2025 | RUBEN SALAS |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 9/15/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/26/2023 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 10/13/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 1/23/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 1/26/2024 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markarian,, Mardiros; Lic. No.: NA53434 | , |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/18/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 4/18/2024 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/23/2024 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/7/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/7/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 5/7/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 5/7/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/3/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 6/3/2024 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 6/3/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Structural Steel Frame | 6/3/2024 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 6/3/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 6/11/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 6/21/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 6/21/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 6/21/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/28/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/28/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/28/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/3/2024 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 7/3/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 7/19/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/19/2024 | Partial Approval | MISAEL ESPARZA |
| Insulation | 7/25/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 8/5/2024 | Approved | MISAEL ESPARZA |
| Pool Piping | 10/2/2024 | Partial Inspection | MISAEL ESPARZA |
| Pre-Gunite | 10/2/2024 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/9/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/9/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 1/9/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 1/9/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 1/9/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/9/2025 | SGSOV Not Required | MISAEL ESPARZA |
| Service/Power Release | 1/9/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 1/9/2025 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 1/9/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/16/2025 | Approved | MISAEL ESPARZA |
| Final | 1/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/16/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 1/16/2025 | Approved | MISAEL ESPARZA |
| Service/Power Release | 1/16/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 1/31/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 1/31/2025 | Approved | MISAEL ESPARZA |