726 W 146TH ST 90247

Certificate Information: 726 W 146TH ST 90247

Application / Permit
23010-10000-03385
Plan Check / Job No.
B23LA15709
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ONE STORY DETACHED ADU AT REAR OF THE PROPERTY PER ORDINANCE.
Permit Issued
Issued on 10/4/2023
Issuing Office
Metro
Current Status
Issued on 10/4/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/22/2023 APPLICANT
Assigned to Plan Check Engineer 8/29/2023 AUNG SOE
Building Plans Picked Up 9/5/2023 APPLICANT
Corrections Issued 9/6/2023 AUNG SOE
Applicant returned to address corrections 9/7/2023 CRISTINA SALAZAR
Applicant returned to address corrections 10/3/2023 MINA HABILI
Plan Check Approved 10/4/2023 STANLEY RAAP
Issued 10/4/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/31/2023 ERIK BEASLEY
Construction near power lines Cleared 9/5/2023 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 9/19/2023 KHAING AYE
Sewer availability Cleared 9/19/2023 KHAING AYE
Low Impact Development (LID) Cleared 9/21/2023 AUNG SOE
Roof/Waste drainage to street Cleared 9/22/2023 ERIK BEASLEY

Contact Information

Contractor J B New Construction Inc; Lic. No.: 923970-B 13923 S CRENSHAW BLVD      HAWTHORNE, CA 90250
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/10/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 10/13/2023 Approved JAMES CHAVEZ
METHANE-Barrier 10/13/2023 Approved JAMES CHAVEZ
METHANE-Subgrade 10/13/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 10/23/2023 Partial Approval JAMES CHAVEZ
Sewer 10/23/2023 Partial Approval JAMES CHAVEZ
Insulation 10/24/2023 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 11/2/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 11/8/2023 Approved JAMES CHAVEZ
Green Building Rough 11/8/2023 Approved JAMES CHAVEZ
HVAC-Rough 11/8/2023 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 11/8/2023 Not Ready for Inspection JAMES CHAVEZ
Insulation 11/13/2023 Approved JOHN KLARIN
Drywall Nailing 11/16/2023 Approved JOHN KLARIN
Special/Order Compliance 7/11/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 1/17/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 1/17/2025 Corrections Issued BEN MOLSTAD
Final 1/17/2025 Corrections Issued BEN MOLSTAD
Green Building Final 1/17/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 1/17/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Rough 1/17/2025 Approved BEN MOLSTAD
METHANE-Final 1/17/2025 Approved BEN MOLSTAD
METHANE-Rough 1/17/2025 Approved BEN MOLSTAD
PLUMBING-Final 1/17/2025 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Not Ready BEN MOLSTAD
Service/Power Release 1/17/2025 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 1/17/2025 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 1/17/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 7/11/2025 Not Ready for Inspection BEN MOLSTAD
Final 7/11/2025 Corrections Issued BEN MOLSTAD
Green Building Final 7/11/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 7/11/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Approved BEN MOLSTAD
Service/Power Release 7/11/2025 Not Ready for Inspection BEN MOLSTAD