5744 N TAMPA AVE 91356
Certificate Information: 5744 N TAMPA AVE 91356
- Application / Permit
- 23010-10000-03383
- Plan Check / Job No.
- B23LA15698
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(2) (1-STORY)
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Valley
- Current Status
- Issued on 1/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | CARLOS MONTES |
| Corrections Issued | 9/14/2023 | CARLOS MONTES |
| Quality Review Completed | 9/15/2023 | KEN GILL |
| Building Plans Picked Up | 9/28/2023 | APPLICANT |
| Applicant returned to address corrections | 2/21/2024 | CARLOS MONTES |
| Plan Check Approved | 1/9/2025 | CARLOS MONTES |
| Issued | 1/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/8/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 7/29/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/29/2024 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 11/25/2024 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 11/25/2024 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 11/25/2024 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 11/25/2024 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 11/25/2024 | NELSON RODRIGUEZ |
| Trees in Parkway | Cleared | 12/23/2024 | RICHARD SANCHEZ |
| Permit | Cleared | 12/27/2024 | RYAN CASTRO |
Contact Information
| Architect | Kivotos,, Juan M; Lic. No.: C26491 | 1323 N NIAGARA STREET BURBANK, CA 91505 |
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/15/2025 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Rough | 1/15/2025 | Partial Approval | MORRIS JACKSON |
| Sewer | 1/15/2025 | Approved | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 2/4/2025 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/4/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2026 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 4/6/2026 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 4/6/2026 | Not Ready for Inspection | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 4/6/2026 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/9/2026 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2026 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 5/11/2026 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 5/11/2026 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 5/14/2026 | Approved | JON MCHUGH |
| HVAC-Rough | 5/14/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 5/14/2026 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 5/14/2026 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 5/29/2026 | Approved | HENRY KIM |
| Green Building Rough | 5/29/2026 | Approved | HENRY KIM |
| Insulation | 5/29/2026 | Corrections Issued | HENRY KIM |
| Verify Sprinkler Sign Off | 5/29/2026 | Approved | HENRY KIM |
| Drywall Nailing | 6/9/2026 | Approved | JON MCHUGH |
| Insulation | 6/9/2026 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 6/9/2026 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 6/15/2026 | Partial Approval | ARUTYUN MADATYAN |