11114-11116 S WILLOWBROOK AVE 90059
Certificate Information: 11114-11116 S WILLOWBROOK AVE 90059
- Application / Permit
- 23010-10000-03381
- Plan Check / Job No.
- B23LA15694
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT EXISTING ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - PER WFPP
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Current Status
- CofO Issued on 12/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 8/31/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/15/2024 | DANIEL ABRAMYAN |
| Issued | 5/31/2024 | APPLICANT |
| CofO in Progress | 12/10/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/10/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/10/2025 | ANSON MAGLASANG |
| CofO Issued | 12/10/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 3/26/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 3/26/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2024 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 10/29/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 10/29/2024 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 11/4/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 11/4/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 11/4/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/21/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 11/21/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 11/21/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/4/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/4/2024 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/21/2025 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 1/24/2025 | Approved | ANTHONY EGSON |
| Wood Frame | 1/24/2025 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 1/28/2025 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 1/30/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/20/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 2/24/2025 | Approved | JOSEPH MCGARRY |
| Wood Frame | 2/24/2025 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 2/27/2025 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/7/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 3/7/2025 | Approved | ANTHONY EGSON |
| Insulation | 3/7/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/12/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/12/2025 | Partial Approval | ANTHONY EGSON |
| Shower Pan | 3/12/2025 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 3/14/2025 | Approved | ANTHONY EGSON |
| Shower Pan | 3/20/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 4/17/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 4/23/2025 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/23/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/1/2025 | Partial Inspection | ANTHONY EGSON |
| Final | 7/10/2025 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Approved | JOHN KLARIN |
| Smoke Detectors | 7/10/2025 | Approved | JOHN KLARIN |
| Final | 10/3/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 10/27/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 10/27/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 10/27/2025 | Approved | ANTHONY EGSON |
| Final | 11/26/2025 | Partial Approval | ARTHUR NEGRETE |
| Final | 12/3/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Service/Power Release | 12/10/2025 | Approved | ANSON MAGLASANG |