426-428 E 111TH ST 90061
Certificate Information: 426-428 E 111TH ST 90061
- Application / Permit
- 23010-10000-03380
- Plan Check / Job No.
- B23LA15691
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH ATTACHED GARAGE
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Current Status
- CofO Issued on 7/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | CARLOS MONTES |
| Corrections Issued | 8/27/2023 | CARLOS MONTES |
| Quality Review Completed | 9/1/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/2/2023 | CARLOS MONTES |
| Plan Check Approved | 11/16/2023 | CARLOS MONTES |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 7/25/2024 | JAMES CHAVEZ |
| Permit Finaled | 7/25/2024 | ANSON MAGLASANG |
| CofO Issued | 7/25/2024 | ANSON MAGLASANG |
| Permit Finaled | 7/25/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/11/2023 | NEIL TUANO |
| Address approval | Cleared | 9/13/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2023 | NEIL TUANO |
| Sewer availability | Cleared | 9/22/2023 | NEIL TUANO |
| Hydrant and Access approval | Cleared | 10/6/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 10/19/2023 | MELINEH AGHAKHABIAN |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/2/2024 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Not Ready for Inspection | JOHN KLARIN |
| Underground Mechanical | 1/8/2024 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Not Ready for Inspection | JOHN KLARIN |
| Insulation | 1/9/2024 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2024 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Partial Approval | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 2/29/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 2/29/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/4/2024 | Corrections Issued | BEN MOLSTAD |
| HVAC-Rough | 3/4/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Rough | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 3/5/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 3/6/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 3/6/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 3/6/2024 | Not Ready for Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 3/7/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 3/7/2024 | Approved | BEN MOLSTAD |
| Insulation | 3/11/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 3/26/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 3/26/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 5/28/2024 | No Access for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 5/30/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 6/3/2024 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Final | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/14/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 6/14/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Green Building Final | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/8/2024 | SGSOV Not Ready | BEN MOLSTAD |
| Service/Power Release | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 7/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 7/10/2024 | Approved | BEN MOLSTAD |
| Final | 7/10/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Final | 7/10/2024 | Approved | BEN MOLSTAD |
| HVAC-Final | 7/10/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 7/10/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 7/10/2024 | Approved | BEN MOLSTAD |
| Smoke Detectors | 7/10/2024 | Approved | BEN MOLSTAD |
| Special/Order Compliance | 7/10/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 7/10/2024 | Approved | BEN MOLSTAD |
| Final | 7/23/2024 | OK to Issue CofO | JAMES CHAVEZ |