5333 W ZOO DR 90027
Certificate Information: 5333 W ZOO DR 90027
- Application / Permit
- 23010-10000-03377
- Plan Check / Job No.
- B23LA15678
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- *eplan*NEW 26'-6"Wx50'-6"Lx12'-0"H SHADESTRUCTURE IN EXISTING RHINOCEROS EXHIBIT. AREA OF WORK IS NOT ACCESSIBLE TO GENERAL PUBLIC.
- Permit Issued
- Issued on 10/31/2023
- Issuing Office
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | RAHEL BEYENE |
| Corrections Issued | 9/11/2023 | RAHEL BEYENE |
| Quality Review Completed | 10/5/2023 | HERNAN ARREOLA |
| Plan Check Approved | 10/26/2023 | RAHEL BEYENE |
| Issued | 10/31/2023 | APPLICANT |
| CofO in Progress | 5/10/2024 | DAVID BURKHEAD |
| CofO Issued | 5/15/2024 | ADAM BURGESS |
| Permit Finaled | 5/15/2024 | ADAM BURGESS |
Permit Application Clearance Information
| Green Code | Cleared | 8/31/2023 | DONALD CRICHLOW |
| ZA Case | Cleared | 9/26/2023 | JAZMIN ROQUE |
| ZI | Cleared | 9/26/2023 | JAZMIN ROQUE |
| DAS Clearance | Cleared | 10/2/2023 | Chad Doi |
| City owned building/parcel | Cleared | 10/11/2023 | RAHEL BEYENE |
| Grading Pre-Inspection | Cleared | 10/12/2023 | ALEXANDER HELFER |
Contact Information
| Contractor | United Riggers & Erectors Inc; Lic. No.: 245451-B | , |
| Engineer | Panek,, Gregory Miles; Lic. No.: C79148 | 138 W BORROMEO AVE PLACENTIA, CA 92870 |
| Engineer | Panek,, Gregory Miles; Lic. No.: NA79148 | , |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/15/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Final | 5/6/2024 | Partial Inspection | DAVID BURKHEAD |
| Footing/Foundation/Slab | 5/6/2024 | Approved | DAVID BURKHEAD |
| Green Building Final | 5/6/2024 | Approved | DAVID BURKHEAD |
| Green Building Rough | 5/6/2024 | Approved | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 5/6/2024 | SGSOV No Gas | DAVID BURKHEAD |
| Smoke Detectors | 5/6/2024 | Approved | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 5/6/2024 | Approved | DAVID BURKHEAD |
| Wood Frame | 5/6/2024 | Approved | DAVID BURKHEAD |
| Final | 5/10/2024 | OK to Issue CofO | DAVID BURKHEAD |