5500 W 98TH ST 90045
Certificate Information: 5500 W 98TH ST 90045
- Application / Permit
- 23010-10000-03361
- Plan Check / Job No.
- B22LA04580
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- **EPLAN*** LAX PROJECT - CONRAC** PROPOSED NEW 6'-6" X 8'-0" CAR CORRAL ATTENDANT BOOTH.
- Permit Issued
- Issued on 2/21/2024
- Issuing Office
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2022 | EDUARDO RODRIGUEZ |
| Corrections Issued | 5/11/2022 | EDUARDO RODRIGUEZ |
| Quality Review Completed | 5/12/2022 | LIPING TENG |
| Applicant returned to address corrections | 5/19/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 7/1/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 7/28/2022 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 2/27/2023 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 3/2/2023 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 7/31/2023 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 8/22/2023 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 8/24/2023 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 9/20/2023 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 10/4/2023 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 1/29/2024 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 2/14/2024 | EDUARDO RODRIGUEZ |
| Issued | 2/21/2024 | APPLICANT |
| CofO in Progress | 9/24/2024 | ALAN NOVAK |
| CofO in Progress | 9/24/2024 | ALAN NOVAK |
| Permit Finaled | 9/24/2024 | NICK LAROCCA |
| CofO Issued | 9/24/2024 | NICK LAROCCA |
| Permit Finaled | 9/24/2024 | NICK LAROCCA |
Permit Application Clearance Information
| Green Code | Cleared | 10/25/2023 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 10/31/2023 | EDUARDO RODRIGUEZ |
| Address approval | Cleared | 11/1/2023 | MARYAM AZARBAYJANI |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2023 | MARYAM AZARBAYJANI |
| Sewer availability | Cleared | 11/1/2023 | MARYAM AZARBAYJANI |
| Airport buildings | Cleared | 11/9/2023 | ANDREW KO |
| Hydrant and Access approval | Cleared | 12/9/2023 | JOHN CONNEALLY |
| City owned building/parcel | Cleared | 12/13/2023 | EDUARDO RODRIGUEZ |
| Project Permit | Cleared | 12/21/2023 | MERCEDES ORTIZ |
| Specific Plan | Cleared | 1/16/2024 | EDUARDO HERMOSO |
Contact Information
| Architect | Demattei,, Anthony James; Lic. No.: C15383 | 1555 BAYSHORE HIGHWAY #300 BURLINGAME, CA 94010 |
| Contractor | Capitol Construction Services Inc; Lic. No.: 864446-B | 11051 VILLAGE SQAURE LANE FISHERS, IN 46038 |
| Engineer | Newhall,, James; Lic. No.: S6641 | 7320 N 14TH DR PHOENIX, AZ 85021 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/28/2024 | Not Ready for Inspection | ALAN NOVAK |
| Drywall Nailing | 9/12/2024 | Approved | ALAN NOVAK |
| Final | 9/12/2024 | OK to Issue CofO | ALAN NOVAK |
| Footing/Foundation/Slab | 9/12/2024 | Approved | ALAN NOVAK |
| Green Building Final | 9/12/2024 | Approved | ALAN NOVAK |
| Green Building Rough | 9/12/2024 | Approved | ALAN NOVAK |
| Reinforced Masonry Frame | 9/12/2024 | Approved | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 9/12/2024 | Approved | ALAN NOVAK |
| Structural Steel Frame | 9/12/2024 | Approved | ALAN NOVAK |
| Verify Sprinkler Sign Off | 9/12/2024 | Approved | ALAN NOVAK |