5203 W 21ST ST 90016

Certificate Information: 5203 W 21ST ST 90016

Application / Permit
23010-10000-03360
Plan Check / Job No.
B23LA15563
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan (N) 3-STORY SINGLE FAMILY DWELLING AT FRONT OF LOT NFPA 13D SPRINKLER THRU-OUT
Permit Issued
Issued on 4/15/2024
Issuing Office
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 JAD BASMA
Corrections Issued 8/26/2023 JAD BASMA
Quality Review Completed 9/5/2023 PRANITA SHAH
Plan Check Approved 4/12/2024 JAD BASMA
Issued 4/15/2024 APPLICANT
CofO in Progress 4/14/2025 ALEJANDRO DE ARTOLA
Permit Finaled 4/14/2025 DEROLD HAUFF
CofO Issued 4/14/2025 DEROLD HAUFF
Permit Finaled 4/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/21/2023 TREVOR QUAN
Frnt yard landscape/Water mgmt Cleared 9/28/2023 FIPE LEILUA
Low Impact Development (LID) Cleared 10/3/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 10/6/2023 CELINA MORENO
Hydrant and Access approval Cleared 10/14/2023 JOHN CONNEALLY
SB8 RUD Cleared 2/28/2024 JASON WELLS
Address approval Cleared 3/5/2024 CHRISTINA BRACO
Sewer availability Cleared 3/13/2024 CHRISTINA BRACO
DAS Clearance Cleared 4/8/2024 NORLITO MEDRANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/1/2024 Partial Inspection ARTHUR NEGRETE
Underground Mechanical 7/1/2024 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 7/18/2024 Partial Approval ARTHUR NEGRETE
Footing/Foundation/Slab 7/18/2024 Partial Inspection ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Approved ARTHUR NEGRETE
Special/Order Compliance 8/5/2024 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Approval ARTHUR NEGRETE
Special/Order Compliance 8/9/2024 Partial Approval AMIR NAZARIAN
BUILDING-Rough-Frame 10/17/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 10/17/2024 Approved ARTHUR NEGRETE
Green Building Rough 10/17/2024 Approved ARTHUR NEGRETE
HVAC-Rough 10/17/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 10/17/2024 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 10/17/2024 Approved ARTHUR NEGRETE
Insulation 10/23/2024 Approved ARTHUR NEGRETE
Drywall Nailing 10/31/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 10/31/2024 Approved ARTHUR NEGRETE
Sewer 12/30/2024 Approved ARTHUR NEGRETE
Underground Mechanical 12/30/2024 Approved ARTHUR NEGRETE
Verify Rec and Parks Fee Memo 12/30/2024 Approved ARTHUR NEGRETE
Underground Mechanical 12/31/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/13/2025 Approved ARTHUR NEGRETE
HVAC-Final 3/13/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 3/13/2025 Approved ARTHUR NEGRETE
Final 3/27/2025 Partial Inspection ARTHUR NEGRETE
Footing/Foundation/Slab 3/27/2025 Approved ARTHUR NEGRETE
Green Building Final 3/27/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 3/27/2025 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 3/27/2025 Approved ARTHUR NEGRETE
Final 4/2/2025 Corrections Issued ARTHUR NEGRETE
Service/Power Release 4/2/2025 Approved ARTHUR NEGRETE
Final 4/11/2025 OK to Issue CofO ALEJANDRO DE ARTOLA