551 W 189TH ST 90248

Certificate Information: 551 W 189TH ST 90248

Application / Permit
23010-10000-03351
Plan Check / Job No.
B23LA10604
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
(eplan) NEW GUARD BOOTH WITH RESTROOM
Permit Issued
Issued on 2/20/2024
Issuing Office
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 YOUNG KIM
Corrections Issued 7/11/2023 YOUNG KIM
Quality Review Completed 7/25/2023 FARUK SEZER
Applicant returned to address corrections 8/18/2023 YOUNG KIM
Applicant returned to address corrections 12/20/2023 YOUNG KIM
Applicant returned to address corrections 2/2/2024 YOUNG KIM
Applicant returned to address corrections 2/14/2024 YOUNG KIM
Plan Check Approved 2/16/2024 YOUNG KIM
Issued 2/20/2024 APPLICANT
CofO in Progress 12/10/2024 JOEY BUCHANAN
CofO Issued 12/12/2024 JOEY BUCHANAN
Permit Finaled 12/12/2024 JOEY BUCHANAN

Permit Application Clearance Information

Miscellaneous Cleared 10/11/2023 YINGSHI HUANG
Address approval Cleared 10/25/2023 ERIK BEASLEY
Roof/Waste drainage to street Cleared 10/25/2023 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/17/2023 ERIK BEASLEY
Sewer availability Cleared 11/17/2023 ERIK BEASLEY
Green Code Cleared 12/19/2023 AARON COSTA
DAS Clearance Cleared 1/25/2024 YOUNG KIM

Contact Information

Architect Cataldo,, John G; Lic. No.: C10457 835 MISSION STREET      SOUTH PASADENA, CA 91030
Contractor Norm Wilson & Sons Inc; Lic. No.: 435700-B       ,
Engineer Aaa, Engineering Desin; Lic. No.: C95446 8031 MAIN ST      STANTON, CA 90680
Engineer Mitchell,, Gregory; Lic. No.: GE2364 22885 E SAVI RANCH PKWY STE E      YORBA LINDA, CA 92887

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/30/2024 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 10/9/2024 Corrections Issued JOEY BUCHANAN
Green Building Rough 10/9/2024 Approved JOEY BUCHANAN
Drywall Nailing 12/9/2024 Approved JOEY BUCHANAN
Final 12/9/2024 OK to Issue CofO JOEY BUCHANAN
Footing/Foundation/Slab 12/9/2024 Approved JOEY BUCHANAN
Green Building Final 12/9/2024 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV No Gas JOEY BUCHANAN
Smoke Detectors 12/9/2024 Approved JOEY BUCHANAN
Structural Steel Frame 12/9/2024 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 12/9/2024 Approved JOEY BUCHANAN
Wood Frame 12/9/2024 Approved JOEY BUCHANAN