868-870 N MADISON AVE 90029

Certificate Information: 868-870 N MADISON AVE 90029

Application / Permit
23010-10000-03344
Plan Check / Job No.
B23LA15525
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Epln: (N) (2) ADUS above Patio Cover. Detached ADUs per Ca Govt Code 65852.2(e)(1)(d) and applicable LAMC 12.22 A.33 (c)-(d), (g).
Permit Issued
Issued on 7/22/2024
Issuing Office
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 ADRIANA LOPEZ
Corrections Issued 8/30/2023 RACHEL BEYENE
Quality Review Completed 10/5/2023 HERNAN ARREOLA
Applicant returned to address corrections 12/13/2023 RACHEL BEYENE
Applicant returned to address corrections 4/11/2024 ADRIANA LOPEZ
Applicant returned to address corrections 5/15/2024 ADRIANA LOPEZ
Applicant returned to address corrections 6/10/2024 ADRIANA LOPEZ
Plan Check Approved 7/22/2024 ADRIANA LOPEZ
Issued 7/22/2024 APPLICANT
CofO in Progress 5/18/2026 FREDDIE RIVERA
Permit Finaled 5/19/2026 DEROLD HAUFF
CofO Issued 5/19/2026 DEROLD HAUFF
Permit Finaled 5/19/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/13/2023 DARIN LAM
Low Impact Development (LID) Cleared 12/22/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/10/2024 DAVID VO
Specific Plan Cleared 3/12/2024 YAMILLET BRIZUELA
Eng Process Fee Ord 176,300 Cleared 3/19/2024 CHRISTINA BRACO
Sewer availability Cleared 3/19/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/2/2025 Partial Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/5/2025 Corrections Issued BRENDAN MORELLI
Pre-Inspection 8/6/2025 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 8/15/2025 Approved FREDDIE RIVERA
Sewer 8/15/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 8/25/2025 Partial Approval FREDDIE RIVERA
Sewer 9/8/2025 Approved FREDDIE RIVERA
Underground Mechanical 9/8/2025 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 10/2/2025 Approved FREDDIE RIVERA
HVAC-Rough 10/2/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 10/2/2025 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 10/7/2025 Partial Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 10/10/2025 Approved FREDDIE RIVERA
Shower Pan 10/10/2025 Approved FREDDIE RIVERA
Special/Order Compliance 10/10/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 10/20/2025 Approved FREDDIE RIVERA
Green Building Rough 10/20/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 10/20/2025 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 10/20/2025 Approved FREDDIE RIVERA
Insulation 11/6/2025 Approved GEM DE OCAMPO
Drywall Nailing 11/10/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/13/2025 Partial Approval DEVON JACKSON
Interior/Exterior Lathing 11/18/2025 Approved FREDDIE RIVERA
ELECTRICAL-Final 4/13/2026 Approved FREDDIE RIVERA
Final 4/13/2026 Corrections Issued FREDDIE RIVERA
Green Building Final 4/13/2026 Approved FREDDIE RIVERA
HVAC-Final 4/13/2026 Approved FREDDIE RIVERA
PLUMBING-Final 4/13/2026 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 4/13/2026 SGSOV Approved FREDDIE RIVERA
Service/Power Release 4/13/2026 Partial Inspection FREDDIE RIVERA
Smoke Detectors 4/13/2026 Approved FREDDIE RIVERA
Special/Order Compliance 4/13/2026 Not Ready for Inspection GEM DE OCAMPO
ELECTRICAL-Final 5/8/2026 Approved FREDDIE RIVERA
Final 5/8/2026 OK to Issue CofO FREDDIE RIVERA
HVAC-Final 5/8/2026 Approved FREDDIE RIVERA
PLUMBING-Final 5/8/2026 Approved FREDDIE RIVERA
Service/Power Release 5/8/2026 Approved FREDDIE RIVERA