1039 W KIPLING AVE 90041
Certificate Information: 1039 W KIPLING AVE 90041
- Application / Permit
- 23010-10000-03314
- Plan Check / Job No.
- B23LA15328
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 35'-4" x 14'-0" DETACHED FULLY ELECTRIC ACCSSORY DWELLING UNIT (MANUFACTURED HOME). STATE APPROVED HOUSE AND FOUNDATION PLANS PER ENGINEER TO COMPLY WITH GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g).
- Permit Issued
- Issued on 2/6/2024
- Issuing Office
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2023 | MADISON ODELL |
| Corrections Issued | 8/23/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 12/15/2023 | MADISON ODELL |
| Plan Check Approved | 1/9/2024 | MADISON O'DELL |
| Issued | 2/6/2024 | APPLICANT |
| CofO in Progress | 4/8/2024 | CRAIG VAUGHAN |
| CofO Issued | 4/8/2024 | DEROLD HAUFF |
| Permit Finaled | 4/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2023 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 11/17/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 12/7/2023 | DAVID LOPEZ |
| Grading Pre-Inspection | Cleared | 12/16/2023 | MADISON O'DELL |
| Miscellaneous | Cleared | 12/20/2023 | ALBERT TAM |
Contact Information
| Contractor | Abodu Inc; Lic. No.: 1073522-B | , |
| Engineer | Denio,, Jordan Paul; Lic. No.: C74796 | 2778 CLAPHAM LN MINDEN, NV 89423 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/28/2024 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 2/28/2024 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 4/1/2024 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 4/5/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 4/5/2024 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 4/5/2024 | Approved | CRAIG VAUGHAN |
| Final | 4/5/2024 | OK to Issue CofO | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/5/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 4/5/2024 | Approved | CRAIG VAUGHAN |
| MERV13>=Final | 4/5/2024 | Approved | CRAIG VAUGHAN |
| MERV13>=Rough | 4/5/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 4/5/2024 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Required | CRAIG VAUGHAN |
| Service/Power Release | 4/5/2024 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/5/2024 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 4/5/2024 | Approved | CRAIG VAUGHAN |