1607 W 37TH ST 90018
Certificate Information: 1607 W 37TH ST 90018
- Application / Permit
- 23010-10000-03289
- Plan Check / Job No.
- B23LA15170
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW IRREGULAR SHAPED, FULLY ELECTRIC DETACHED 31'-4" x 33'-0" ACCESSORY DWELLING UNIT (870 SF) TO COMPLY WITH PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). WORK DONE PER WFPP.
- Permit Issued
- Issued on 9/23/2024
- Issuing Office
- Current Status
- Issued on 9/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | ALFRED RAMIREZ |
| Corrections Issued | 1/5/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 3/16/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 3/26/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 3/27/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 6/26/2024 | MADISON O'DELL |
| Issued | 9/23/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/18/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 6/18/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/24/2024 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2025 | Partial Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 10/7/2025 | Approved | SABAS ALONSO |
| METHANE-Barrier | 10/7/2025 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 10/7/2025 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 10/17/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 10/20/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/18/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/18/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/30/2025 | Partial Approval | ALEX COLIN |
| Green Building Rough | 1/6/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 1/6/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/9/2026 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/14/2026 | Approved | SABAS ALONSO |
| Insulation | 1/14/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 1/20/2026 | Partial Approval | GEM DE OCAMPO |
| Drywall Nailing | 2/5/2026 | Approved | SABAS ALONSO |
| Sewer | 2/5/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/20/2026 | Approved | SABAS ALONSO |
| Shower Pan | 2/20/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/20/2026 | Approved | SABAS ALONSO |
| Final | 5/6/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 5/6/2026 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 5/6/2026 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 5/6/2026 | Approved | SABAS ALONSO |
| Smoke Detectors | 5/6/2026 | Approved | SABAS ALONSO |