2854 N ROSANNA ST 90039

Certificate Information: 2854 N ROSANNA ST 90039

Application / Permit
23010-10000-03273
Plan Check / Job No.
B23LA15047
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: New 1-Story Detached ADU per LAMC 12.22 A.33 (c)-(d), All Work Done per WFPP
Permit Issued
Issued on 6/7/2024
Issuing Office
Current Status
CofO Issued on 12/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2023 APPLICANT
Assigned to Plan Check Engineer 8/25/2023 ALFREDO JARA
Corrections Issued 8/28/2023 ALFREDO JARA
Applicant returned to address corrections 5/21/2024 DAVID CASTILLO
Plan Check Approved 6/7/2024 DAVID CASTILLO
Issued 6/7/2024 APPLICANT
CofO in Progress 12/5/2024 LUIS CASTRO
Permit Finaled 12/7/2024 DEROLD HAUFF
CofO Issued 12/7/2024 DEROLD HAUFF
Permit Finaled 12/7/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 9/19/2023 NATHAN ROMINE
Miscellaneous Cleared 9/21/2023 NATHAN ROMINE
Address approval Cleared 9/22/2023 NEIL TUANO
Eng Process Fee Ord 176,300 Cleared 9/22/2023 NEIL TUANO
Sewer availability Cleared 9/22/2023 NEIL TUANO
Low Impact Development (LID) Cleared 4/29/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 5/5/2024 ADRIAN SANCHEZ
Tenant Habitability Plan Cleared 5/15/2024 HUGO GARRIDO GARZA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/22/2024 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 7/29/2024 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/1/2024 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 8/22/2024 Approved BRENDAN MORELLI
Special/Order Compliance 8/22/2024 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/26/2024 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/30/2024 Approved ANTHONY RAMOS
Shower Pan 8/30/2024 Approved ANTHONY RAMOS
Insulation 9/4/2024 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 9/4/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/9/2024 Conditional Approval LILIANA PORTILLO
Drywall Nailing 9/9/2024 Approved LILIANA PORTILLO
Green Building Rough 9/9/2024 Approved LILIANA PORTILLO
MERV13>=Rough 9/9/2024 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 9/9/2024 Approved LILIANA PORTILLO
Underground Mechanical 9/27/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 10/25/2024 Approved LUIS CASTRO
ELECTRICAL-Final 10/25/2024 Approved LUIS CASTRO
Final 10/25/2024 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 10/25/2024 Approved LUIS CASTRO
HVAC-Final 10/25/2024 Approved LUIS CASTRO
MERV13>=Final 10/25/2024 Approved LUIS CASTRO
PLUMBING-Final 10/25/2024 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV No Gas LUIS CASTRO
Service/Power Release 10/25/2024 Corrections Issued LUIS CASTRO
Smoke Detectors 10/25/2024 Approved LUIS CASTRO
Final 11/13/2024 Corrections Issued LUIS CASTRO
Service/Power Release 11/13/2024 Not Ready for Inspection LUIS CASTRO
Final 12/4/2024 OK to Issue CofO LUIS CASTRO
Service/Power Release 12/4/2024 Approved LUIS CASTRO