10926 1/2 S GRAPE ST 90059
Certificate Information: 10926 1/2 S GRAPE ST 90059
- Application / Permit
- 23010-10000-03268
- Plan Check / Job No.
- B23LA15029
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan new 2 story ADU 800 sq ft. Ground level 400 sq ft and second level 400 sq ft including 3 bedrooms, living room, kitchen, full bath per GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) (NFPA 13D fire sprinkler system is required) .
- Permit Issued
- Issued on 11/4/2024
- Issuing Office
- Current Status
- Issued on 11/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | NGHI SU |
| Corrections Issued | 9/25/2023 | NGHI SU |
| Quality Review Completed | 10/25/2023 | FARUK SEZER |
| Applicant returned to address corrections | 3/7/2024 | NGHI SU |
| Applicant returned to address corrections | 6/7/2024 | NGHI SU |
| Applicant returned to address corrections | 8/23/2024 | NGHI SU |
| Plan Check Approved | 9/30/2024 | NGHI SU |
| Issued | 11/4/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 6/10/2024 | MARTIN FRAGOSO |
| Address approval | Cleared | 8/30/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 8/30/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 8/31/2024 | JESSICA OPINION |
| ZI | Cleared | 9/4/2024 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tagudar,, Fred; Lic. No.: C33612 | 255 W 5TH ST APT 706 SAN PEDRO, CA 90731 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/10/2025 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 1/27/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/27/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 1/30/2025 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 2/5/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/5/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2025 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/17/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 10/17/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 12/9/2025 | Partial Approval | ARTHUR NEGRETE |
| Green Building Rough | 12/22/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 12/22/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 12/22/2025 | Partial Inspection | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 1/27/2026 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 5/5/2026 | Partial Approval | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 5/5/2026 | Approved | ARTHUR NEGRETE |