1554 W 55TH ST 90062

Certificate Information: 1554 W 55TH ST 90062

Application / Permit
23010-10000-03267
Plan Check / Job No.
B23LA15028
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) (2-STORY)
Permit Issued
Issued on 6/21/2024
Issuing Office
Current Status
CofO Issued on 3/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 CARLOS MONTES
Corrections Issued 8/19/2023 CARLOS MONTES
Quality Review Completed 8/24/2023 GARO TELMI
Applicant returned to address corrections 10/5/2023 CARLOS MONTES
Applicant returned to address corrections 12/7/2023 CARLOS MONTES
Applicant returned to address corrections 2/2/2024 CARLOS MONTES
Applicant returned to address corrections 3/27/2024 CARLOS MONTES
Applicant returned to address corrections 5/30/2024 CARLOS MONTES
Plan Check Approved 6/20/2024 CARLOS MONTES
Issued 6/21/2024 APPLICANT
CofO in Progress 3/10/2025 SABAS ALONSO
CofO Issued 3/12/2025 DEROLD HAUFF
Permit Finaled 3/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/14/2023 CHRISTINA BRACO
Community Plan Implem. Overlay Cleared 9/18/2023 RAFAEL FONTES
Eng Process Fee Ord 176,300 Cleared 9/19/2023 CHRISTINA BRACO
Sewer availability Cleared 9/19/2023 CHRISTINA BRACO
Community Plan Implem. Overlay Cleared 9/20/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 9/20/2023 ERNEST TSE
Community Plan Implem. Overlay Cleared 9/25/2023 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 9/25/2023 CHRISTINA BRACO
Community Plan Implem. Overlay Cleared 11/29/2023 RIDWAN HARDY

Contact Information

Contractor United Builders & Development Inc; Lic. No.: 1066908-B       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/28/2024 Partial Approval SABAS ALONSO
Sewer 6/28/2024 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 6/28/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 7/2/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Inspection MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 8/8/2024 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Approved SABAS ALONSO
Gas Test 8/8/2024 Not Ready for Inspection SABAS ALONSO
Green Building Rough 8/8/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 8/8/2024 Approved SABAS ALONSO
Rough-Elec/Plmb/HVAC 8/8/2024 Corrections Issued SABAS ALONSO
Sewer 8/8/2024 Approved SABAS ALONSO
Underground Mechanical 8/8/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/19/2024 Approved CRAIG DAVIS
ELECTRICAL-Rough 8/19/2024 Approved CRAIG DAVIS
Green Building Rough 8/19/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 8/19/2024 Approved CRAIG DAVIS
PLUMBING-Rough 8/19/2024 Approved CRAIG DAVIS
Insulation 8/22/2024 Approved MICHAEL LEWIS
Shower Pan 8/22/2024 Approved MICHAEL LEWIS
Drywall Nailing 8/27/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 8/27/2024 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 8/30/2024 Approved ALEX COLIN
Final 11/19/2024 Corrections Issued SABAS ALONSO
Green Building Final 11/19/2024 Approved SABAS ALONSO
Service/Power Release 11/19/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 11/19/2024 Corrections Issued SABAS ALONSO
Final 11/25/2024 Corrections Issued SABAS ALONSO
Smoke Detectors 11/25/2024 Approved SABAS ALONSO
Final 3/7/2025 OK to Issue CofO SABAS ALONSO
Footing/Foundation/Slab 3/7/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/7/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 3/7/2025 Not Ready for Inspection SABAS ALONSO