8511 S RAYMOND AVE 90044
Certificate Information: 8511 S RAYMOND AVE 90044
- Application / Permit
- 23010-10000-03235
- Plan Check / Job No.
- B23LA14885
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/24/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/30/2023 | KEN GILL |
| Building Plans Picked Up | 9/6/2023 | APPLICANT |
| Plan Check Approved | 4/22/2024 | MAHNAZ NOURHASHEMI |
| Issued | 5/31/2024 | APPLICANT |
| CofO in Progress | 5/27/2026 | JOHN QUINTANILLA |
| Permit Finaled | 5/28/2026 | DEROLD HAUFF |
| CofO Issued | 5/28/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2023 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 9/21/2023 | JESSICA OPINION |
| Community Plan Implem. Overlay | Cleared | 2/5/2024 | MANERI ROMAN |
| Low Impact Development (LID) | Cleared | 2/12/2024 | MELINEH AGHAKHABIAN |
| Historic Resource Verification | Cleared | 2/14/2024 | RAFAEL FONTES |
| Roof/Waste drainage to street | Cleared | 2/14/2024 | AMBER CAMPBELL |
| Redevelopment Project Area | Cleared | 2/29/2024 | YASMINE BASHIRI |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | 3627 E FIRST STREET LOS ANGELES, CA 90063 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/21/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 6/21/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Underground Mechanical | 6/21/2024 | Approved | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 6/28/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Corrections Issued | MICHAEL LEWIS |
| Deputy Wood Construction | 7/12/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/6/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 9/6/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/6/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 9/10/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 9/10/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 9/10/2024 | Approved | MICHAEL LEWIS |
| Insulation | 9/27/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Insulation | 10/2/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/2/2024 | Partial Approval | ALEX COLIN |
| Drywall Nailing | 10/7/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/7/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Rough | 12/11/2024 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 12/11/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Not Ready | LUIS CASTRO |
| HVAC-Final | 1/29/2026 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 1/29/2026 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 2/6/2026 | Approved | JOHN QUINTANILLA |
| Green Building Final | 2/6/2026 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 2/6/2026 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2026 | SGSOV Not Ready | JOHN QUINTANILLA |
| Final | 5/12/2026 | Corrections Issued | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Not Required | JOHN QUINTANILLA |
| Service/Power Release | 5/12/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Final | 5/26/2026 | OK to Issue CofO | JOHN QUINTANILLA |
| Service/Power Release | 5/26/2026 | Approved | JOHN QUINTANILLA |