11845 W PACIFIC AVE 90066

Certificate Information: 11845 W PACIFIC AVE 90066

Application / Permit
23010-10000-03231
Plan Check / Job No.
B23LA14873
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan.New 2-Story Single Family Dwelling with Attached Garage
Permit Issued
Issued on 1/16/2024
Issuing Office
Current Status
CofO Issued on 9/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 MAHNAZ NOURHASHEMI
Corrections Issued 9/3/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 9/12/2023 TU HUA
Plan Check Approved 1/5/2024 MAHNAZ NOURHASHEMI
Issued 1/16/2024 APPLICANT
CofO in Progress 9/5/2024 DAVID FEILER
Permit Finaled 9/7/2024 RICHARD STEINBACH
CofO Issued 9/7/2024 RICHARD STEINBACH
Permit Finaled 9/7/2024 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 9/12/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/13/2023 DARIN LAM
Sewer availability Cleared 9/13/2023 DARIN LAM
Address approval Cleared 10/4/2023 DARIN LAM
Hydrant and Access approval Cleared 10/6/2023 JOHN CONNEALLY
Disturb/Remove Protected Trees Cleared 10/19/2023 ADALBERTO VERA
Trees in Parkway Cleared 11/13/2023 ADALBERTO VERA
Specific Plan Cleared 11/20/2023 FREDDY GARCIA
Low Impact Development (LID) Cleared 11/21/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 11/22/2023 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/1/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 3/1/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 3/1/2024 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 3/1/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 3/5/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/26/2024 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 4/2/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/2/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 4/3/2024 Approved JESUS RODRIGUEZ
Deputy Wood Construction 4/5/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/5/2024 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/5/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/12/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 4/12/2024 Approved JESUS RODRIGUEZ
Green Building Rough 4/12/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/12/2024 Approved JESUS RODRIGUEZ
Shower Pan 4/12/2024 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 4/12/2024 Approved JESUS RODRIGUEZ
Insulation 4/16/2024 Conditional Approval JESUS RODRIGUEZ
Insulation 4/17/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/17/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 4/19/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/19/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/1/2024 Approved JESUS RODRIGUEZ
Final 8/1/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 8/1/2024 Approved JESUS RODRIGUEZ
HVAC-Final 8/1/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 8/1/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Not Required JESUS RODRIGUEZ
Service/Power Release 8/1/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 8/1/2024 Approved JESUS RODRIGUEZ
Final 9/5/2024 OK to Issue CofO DAVID FEILER