240-240 1/2 N DILLON ST 90026

Certificate Information: 240-240 1/2 N DILLON ST 90026

Application / Permit
23010-10000-03223
Plan Check / Job No.
B23LA14416
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
*eplan* NEW 3-STORY DUPLEX WITH ATTACHED ADU PER CA Govt. Code 65852.2(e)(1)(C) (REAR LOT)
Permit Issued
Issued on 2/12/2024
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 MAHNAZ NOURHASHEMI
Corrections Issued 8/10/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 8/16/2023 TU HUA
Applicant returned to address corrections 10/27/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 2/2/2024 MAHNAZ NOURHASHEMI
Issued 2/12/2024 APPLICANT
CofO in Progress 8/25/2025 FREDDIE RIVERA
Permit Finaled 8/27/2025 DEROLD HAUFF
CofO Issued 8/27/2025 DEROLD HAUFF
Permit Finaled 8/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/31/2023 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 9/5/2023 AMBER CAMPBELL
Sewer availability Cleared 9/5/2023 AMBER CAMPBELL
SB8 RUD Cleared 9/21/2023 JAMES MCCARTHY
Hydrant and Access approval Cleared 10/11/2023 MATTHEW CRAIG
GPI Written Notices Cleared 10/27/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 10/27/2023 MAHNAZ NOURHASHEMI
Low Impact Development (LID) Cleared 11/29/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/1/2023 AMBER CAMPBELL
DAS Clearance Cleared 1/25/2024 MAHNAZ NOURHASHEMI

Contact Information

Contractor C S W F Construction Inc; Lic. No.: 1021458-B       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 2/15/2024 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 4/26/2024 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 4/26/2024 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 5/1/2024 Corrections Issued FREDDIE RIVERA
METHANE-Barrier 5/1/2024 Partial Inspection FREDDIE RIVERA
METHANE-Subgrade 5/1/2024 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/2/2024 Partial Approval FREDDIE RIVERA
Pre-Inspection 5/2/2024 Partial Approval FREDDIE RIVERA
Deputy Other (see comments) 5/15/2024 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 5/16/2024 Approved FREDDIE RIVERA
METHANE-Barrier 5/16/2024 Approved FREDDIE RIVERA
METHANE-Subgrade 5/16/2024 Approved FREDDIE RIVERA
Sewer 5/24/2024 Approved FREDDIE RIVERA
Underground Mechanical 5/24/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 9/17/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 9/17/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/24/2024 Corrections Issued LUIS CASTRO
PLUMBING-Rough 9/24/2024 Approved LUIS CASTRO
ELECTRICAL-Rough 9/26/2024 Approved FREDDIE RIVERA
HVAC-Rough 9/26/2024 Corrections Issued FREDDIE RIVERA
METHANE-Rough 9/26/2024 Corrections Issued FREDDIE RIVERA
HVAC-Rough 10/1/2024 Conditional Approval FREDDIE RIVERA
Pre-Inspection 10/1/2024 Corrections Issued FREDDIE RIVERA
Deputy Wood Construction 10/2/2024 Conditional Approval FREDDIE RIVERA
HVAC-Rough 10/3/2024 Approved FREDDIE RIVERA
METHANE-Rough 10/3/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 11/5/2024 Partial Inspection FREDDIE RIVERA
Green Building Rough 11/5/2024 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 11/5/2024 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 11/5/2024 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 11/5/2024 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 11/7/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 11/8/2024 Corrections Issued FREDDIE RIVERA
Green Building Rough 11/8/2024 Approved FREDDIE RIVERA
MERV13>=Rough 11/8/2024 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 11/8/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/19/2024 Conditional Approval FREDDIE RIVERA
Insulation 11/19/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/19/2024 Not Ready for Inspection FREDDIE RIVERA
Shower Pan 11/19/2024 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 11/21/2024 Approved FREDDIE RIVERA
Shower Pan 11/21/2024 Approved FREDDIE RIVERA
Drywall Nailing 12/5/2024 Approved FREDDIE RIVERA
Underground Mechanical 3/25/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 5/27/2025 Corrections Issued FREDDIE RIVERA
HVAC-Final 5/27/2025 Approved FREDDIE RIVERA
ELECTRICAL-Final 6/3/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 6/5/2025 Approved FREDDIE RIVERA
PLUMBING-Final 6/17/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/27/2025 Approved FREDDIE RIVERA
Final 6/27/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 6/27/2025 Approved FREDDIE RIVERA
MERV13>=Final 6/27/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Not Ready FREDDIE RIVERA
Service/Power Release 6/27/2025 Partial Inspection FREDDIE RIVERA
Smoke Detectors 6/27/2025 Approved FREDDIE RIVERA
Service/Power Release 7/3/2025 Not Ready for Inspection JEFFREY MEAD
Final 7/8/2025 Conditional Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/8/2025 SGSOV Approved FREDDIE RIVERA
Service/Power Release 7/8/2025 Approved FREDDIE RIVERA
Final 8/11/2025 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 8/11/2025 Approved FREDDIE RIVERA