927 E 41ST PL 90011
Certificate Information: 927 E 41ST PL 90011
- Application / Permit
- 23010-10000-03219
- Plan Check / Job No.
- B23LA14799
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ADU PER LAMC 12.22 A.33 (c) AND (d)
- Permit Issued
- Issued on 3/15/2024
- Issuing Office
- Metro
- Current Status
- Issued on 3/15/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | ADRIANA LOPEZ |
| Corrections Issued | 9/5/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 9/8/2023 | KEN GILL |
| Building Plans Picked Up | 9/11/2023 | APPLICANT |
| Plan Check Approved | 3/7/2024 | ADRIANA LOPEZ |
| Issued | 3/15/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2023 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2023 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/6/2023 | DAVID LOPEZ |
| Low Impact Development (LID) | Cleared | 2/9/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 2/11/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | J J Y Construction Co; Lic. No.: 925414-B | 947 SOUTH HOOVER STREET #108 LOS ANGELES, CA 90006 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 4/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/26/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 4/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/26/2024 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 9/9/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 9/11/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 11/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/26/2024 | Partial Approval | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/26/2024 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Rough | 1/2/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 1/2/2025 | Approved | NICHOLAS LOPEZ |
| Special/Order Compliance | 1/2/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Rough | 1/14/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 1/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 2/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/14/2025 | Partial Approval | RONNIE MEDINA |
| Interior/Exterior Lathing | 7/17/2025 | Partial Inspection | RONNIE MEDINA |
| BUILDING-Rough-Frame | 7/18/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 7/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/18/2025 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 8/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 8/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 8/11/2025 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 8/26/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 8/26/2025 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 9/4/2025 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 1/6/2026 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 1/9/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/3/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/10/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/11/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 2/13/2026 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Service/Power Release | 2/13/2026 | Approved | ALEJANDRO DE ARTOLA |