2127 W AARON ST 90026

Certificate Information: 2127 W AARON ST 90026

Application / Permit
23010-10000-03209
Plan Check / Job No.
B23LA14766
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY SFD WITH ATTACHED GARAGE (FRONT UNIT)
Permit Issued
Issued on 3/6/2024
Issuing Office
Metro
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 CARLOS MONTES
Corrections Issued 8/15/2023 CARLOS MONTES
Quality Review Completed 8/18/2023 KEN GILL
Building Plans Picked Up 8/28/2023 APPLICANT
Applicant returned to address corrections 11/16/2023 CARLOS MONTES
Applicant returned to address corrections 12/21/2023 CARLOS MONTES
Applicant returned to address corrections 1/24/2024 CARLOS MONTES
Plan Check Approved 3/6/2024 CARLOS MONTES
Issued 3/6/2024 APPLICANT
CofO in Progress 8/11/2025 HAMIK HARTOUNIAN
Permit Finaled 8/12/2025 DEROLD HAUFF
CofO Issued 8/12/2025 DEROLD HAUFF
Permit Finaled 8/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/18/2023 WALLIE JONG
Highway dedication Cleared 9/18/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/19/2023 WALLIE JONG
BHO/Hillside ordinance Cleared 9/21/2023 KATHERINE MENDOZA
BHO/Hillside ordinance Cleared 9/21/2023 KATHERINE MENDOZA
BHO/Hillside ordinance Cleared 9/21/2023 KATHERINE MENDOZA
BHO/Hillside ordinance Cleared 9/21/2023 KATHERINE MENDOZA
BHO/Hillside ordinance Cleared 9/21/2023 KATHERINE MENDOZA
Sewer availability Cleared 9/21/2023 WALLIE JONG
SB8 RUD Cleared 10/12/2023 ALYSSA FLORES
Hydrant and Access approval Cleared 10/25/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 11/27/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/28/2023 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 11/30/2023 JOE TAM
GPI Written Notices Cleared 3/6/2024 CARLOS MONTES
Grading Pre-Inspection Cleared 3/6/2024 CARLOS MONTES

Contact Information

Architect Feagins,, Larry; Lic. No.: C27009 669 N THIRD AVENUE      UPLAND, CA 91786
Contractor Residential Alchemists; Lic. No.: 1098394-B 2088 S ATLANTIC BLVD #276      MONTEREY PARK, CA 91754
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/7/2024 Corrections Issued BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 5/14/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/14/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/14/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/15/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/15/2024 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/29/2024 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/29/2024 Partial Approval SCOTT FINNILA
Underground Mechanical 5/29/2024 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 7/11/2024 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/11/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/5/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/5/2024 Corrections Issued HAMIK HARTOUNIAN
Deputy Reinf. Concrete 9/19/2024 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/19/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/24/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Not Ready for Inspection ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Not Ready for Inspection WILLIAM SIERRA
Deputy Wood Construction 12/23/2024 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 12/31/2024 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 12/31/2024 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/6/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 1/6/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/7/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 1/7/2025 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 1/14/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/23/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 1/23/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 1/27/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/27/2025 Partial Approval HAMIK HARTOUNIAN
Shower Pan 1/27/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Shower Pan 1/29/2025 Corrections Issued HAMIK HARTOUNIAN
Shower Pan 1/31/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/10/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 2/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
MERV13>=Rough 2/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 2/10/2025 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/18/2025 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 2/18/2025 Approved FREDDIE RIVERA
Green Building Rough 2/18/2025 Approved FREDDIE RIVERA
MERV13>=Rough 2/18/2025 Approved FREDDIE RIVERA
Verify Sprinkler Sign Off 2/18/2025 Approved FREDDIE RIVERA
Insulation 2/25/2025 Not Ready for Inspection JOSH MEISTER
BUILDING-Rough-Frame 2/26/2025 Approved HAMIK HARTOUNIAN
Insulation 2/26/2025 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/5/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/5/2025 Approved HAMIK HARTOUNIAN
Sewer 4/24/2025 Approved ALEX COLIN
ELECTRICAL-Final 7/29/2025 Corrections Issued BRENDAN MORELLI
Service/Power Release 7/29/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 7/31/2025 Approved HAMIK HARTOUNIAN
HVAC-Final 7/31/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Final 7/31/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 7/31/2025 Approved HAMIK HARTOUNIAN
Final 8/7/2025 OK to Issue CofO HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/7/2025 Approved HAMIK HARTOUNIAN
Green Building Final 8/7/2025 Approved HAMIK HARTOUNIAN
MERV13>=Final 8/7/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/7/2025 SGSOV Not Ready HAMIK HARTOUNIAN
Service/Power Release 8/7/2025 Approved HAMIK HARTOUNIAN
Smoke Detectors 8/7/2025 Approved HAMIK HARTOUNIAN