12042 W MAXWELLTON ROAD 91604
Certificate Information: 12042 W MAXWELLTON ROAD 91604
- Application / Permit
- 23010-10000-03207
- Plan Check / Job No.
- B23LA14748
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. New detached ADU per GCS 65852.2(e)(1)(A) AND LAMC 12.22 A.33(c),(d) AND (g), with fire sprinkler NFPA 13D throughout
- Permit Issued
- Issued on 10/17/2024
- Issuing Office
- Current Status
- CofO in Progress on 6/1/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2023 | JOHNPAUL ISIP |
| Corrections Issued | 8/16/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 9/11/2024 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 9/18/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/1/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 10/16/2024 | REZA HAGHIGHAT |
| Issued | 10/17/2024 | APPLICANT |
| CofO in Progress | 6/1/2026 | CHRISTOPHE COCHRAN |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/14/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 1/11/2024 | PATRICK LOPEZ |
| ZI | Cleared | 2/8/2024 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 3/27/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/27/2024 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 9/15/2024 | JOHNPAUL ISIP |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/17/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Underground Mechanical | 12/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 12/27/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 12/31/2024 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/2/2025 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/14/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 2/14/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 3/4/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/10/2025 | Partial Approval | MISAEL ESPARZA |
| Insulation | 3/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 3/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/1/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 4/8/2025 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Final | 3/19/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 3/19/2026 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 5/6/2026 | Approved | JOSE AVILA |
| Final | 5/22/2026 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/22/2026 | Approved | CHRISTOPHE COCHRAN |
| Green Building Final | 5/22/2026 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2026 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/22/2026 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 5/22/2026 | Approved | CHRISTOPHE COCHRAN |
| Final | 5/28/2026 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/28/2026 | Approved | CHRISTOPHE COCHRAN |