12042 W MAXWELLTON ROAD 91604

Certificate Information: 12042 W MAXWELLTON ROAD 91604

Application / Permit
23010-10000-03207
Plan Check / Job No.
B23LA14748
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. New detached ADU per GCS 65852.2(e)(1)(A) AND LAMC 12.22 A.33(c),(d) AND (g), with fire sprinkler NFPA 13D throughout
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
CofO in Progress on 6/1/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/15/2023 JOHNPAUL ISIP
Corrections Issued 8/16/2023 JOHNPAUL ISIP
Applicant returned to address corrections 9/11/2024 REZA HAGHIGHAT
Applicant returned to address corrections 9/18/2024 DAVID CASTILLO
Applicant returned to address corrections 10/1/2024 JOHNPAUL ISIP
Plan Check Approved 10/16/2024 REZA HAGHIGHAT
Issued 10/17/2024 APPLICANT
CofO in Progress 6/1/2026 CHRISTOPHE COCHRAN

Permit Application Clearance Information

Address approval Cleared 10/14/2023 CARLOS AGUILERA
Sewer availability Cleared 10/14/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 1/11/2024 PATRICK LOPEZ
ZI Cleared 2/8/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 3/27/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/27/2024 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 9/15/2024 JOHNPAUL ISIP

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/17/2024 Corrections Issued CHRISTOPHE COCHRAN
Underground Mechanical 12/20/2024 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 12/27/2024 Corrections Issued CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 12/31/2024 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 1/2/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/14/2025 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 2/14/2025 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/4/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/4/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 3/4/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 3/4/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 3/4/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/4/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/10/2025 Partial Approval MISAEL ESPARZA
Insulation 3/20/2025 Approved CHRISTOPHE COCHRAN
Shower Pan 3/20/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/1/2025 Approved CHRISTOPHE COCHRAN
Drywall Nailing 4/8/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 3/19/2026 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 3/19/2026 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 5/6/2026 Approved JOSE AVILA
Final 5/22/2026 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/22/2026 Approved CHRISTOPHE COCHRAN
Green Building Final 5/22/2026 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/22/2026 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 5/22/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 5/22/2026 Approved CHRISTOPHE COCHRAN
Final 5/28/2026 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 5/28/2026 Approved CHRISTOPHE COCHRAN