2678 S HARCOURT AVE 90016

Certificate Information: 2678 S HARCOURT AVE 90016

Application / Permit
23010-10000-03192
Plan Check / Job No.
B23LA14646
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. PROPOSED 2-STORY DETACHED ADU WITH ATTACHED 2 - CAR GARAGE AND UNCOVERED BALCONY
Permit Issued
Issued on 10/23/2024
Issuing Office
Current Status
Issued on 10/23/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/8/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 CRYSTEL MAALOUF
Corrections Issued 8/30/2023 CRYSTEL MAALOUF
Quality Review Completed 9/1/2023 GARO TELMI
Plan Check Approved 10/15/2024 CRYSTEL MAALOUF
Issued 10/23/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/6/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 10/12/2023 DAVID LOPEZ
Sewer availability Cleared 10/12/2023 DAVID LOPEZ
Low Impact Development (LID) Cleared 3/18/2024 LUIS CRUZ
Construction near power lines Cleared 5/6/2024 RIDWAN HARDY
Roof/Waste drainage to street Cleared 8/19/2024 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Banning,, George Kwame; Lic. No.: NA53074       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/2/2025 No Access for Inspection ROBERT CORNELL
PLUMBING-Rough 5/14/2025 Partial Approval RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 5/15/2025 No Access for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 5/20/2025 Approved JOSE MACIAS
Excavation/Setback/Form/Re-Bar 5/29/2025 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/3/2025 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 7/23/2025 Partial Approval JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 10/1/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 10/10/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 10/10/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 10/10/2025 Approved WILLIAM SIERRA
Green Building Rough 10/10/2025 Not Ready for Inspection WILLIAM SIERRA
HVAC-Rough 10/10/2025 Approved WILLIAM SIERRA
PLUMBING-Rough 10/10/2025 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 10/10/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 10/24/2025 Approved JUSTIN HAWLEY
Green Building Rough 11/17/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 11/17/2025 Partial Approval JUSTIN HAWLEY
Insulation 1/9/2026 Approved WILLIAM SIERRA
Drywall Nailing 1/21/2026 Approved JUSTIN HAWLEY
Shower Pan 1/28/2026 Approved GEM DE OCAMPO
Interior/Exterior Lathing 2/10/2026 Approved WILLIAM SIERRA
Underground Mechanical 5/5/2026 Partial Approval JUSTIN HAWLEY
PLUMBING-Rough 5/7/2026 Approved JUSTIN HAWLEY
Underground Mechanical 6/10/2026 Approved JUSTIN HAWLEY