1428 3/4 W 59TH ST 90047

Certificate Information: 1428 3/4 W 59TH ST 90047

Application / Permit
23010-10000-03112
Plan Check / Job No.
B23LA14211
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1 STORY ADU (all electric)
Permit Issued
Issued on 11/6/2023
Issuing Office
Current Status
CofO Issued on 6/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 HERNAN ARREOLA
Corrections Issued 8/13/2023 HERNAN ARREOLA
Quality Review Completed 8/24/2023 PETER KIM
Plan Check Approved 10/25/2023 HERNAN ARREOLA
Issued 11/6/2023 APPLICANT
CofO in Progress 6/8/2026 LUIS CASTRO
Permit Finaled 6/18/2026 DEROLD HAUFF
CofO Issued 6/18/2026 DEROLD HAUFF
Permit Finaled 6/18/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/16/2023 CELINA MORENO
Roof/Waste drainage to street Cleared 10/17/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/24/2023 CELINA MORENO
Sewer availability Cleared 10/24/2023 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Nagra,, Sukhdeep Singh; Lic. No.: C84908 PO BOX 1836      YUBA CITY, CA 95992

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/31/2024 Corrections Issued RONNIE MINDANAO
Underground Mechanical 2/22/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/23/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Underground Mechanical 2/23/2024 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 2/27/2024 Corrections Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 3/5/2024 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval CRAIG DAVIS
Interior/Exterior Lathing 6/4/2024 Approved CRAIG DAVIS
ELECTRICAL-Rough 9/6/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 9/6/2024 Corrections Issued MICHAEL LEWIS
Rough-Elec/Plmb/HVAC 10/9/2024 Conditional Approval JOHN QUINTANILLA
ELECTRICAL-Rough 1/15/2025 Corrections Issued BARRY HACHE
Rough-Elec/Plmb/HVAC 1/15/2025 No Access for Inspection BARRY HACHE
HVAC-Rough 1/23/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 3/4/2025 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 3/4/2025 Approved OSVALDO PARAMO
Insulation 6/5/2025 Corrections Issued ANTHONY RAMOS
Insulation 7/15/2025 Approved DEVON JACKSON
Drywall Nailing 8/19/2025 Approved BARRY HACHE
Green Building Rough 8/19/2025 Approved BARRY HACHE
Interior/Exterior Lathing 10/16/2025 Approved ALEX COLIN
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Not Ready BARRY HACHE
BUILDING-Rough-Frame 4/9/2026 Approved RAUL BARAJAS
Final 4/9/2026 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 4/9/2026 Approved RAUL BARAJAS
Green Building Final 4/9/2026 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 4/9/2026 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 4/9/2026 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 4/9/2026 Approved RAUL BARAJAS
Final 4/17/2026 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/17/2026 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/17/2026 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 4/17/2026 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 4/17/2026 Approved ENRIQUE MIRELES
Final 5/14/2026 Corrections Issued LUIS CASTRO
Service/Power Release 5/14/2026 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 6/1/2026 Approved LUIS CASTRO
ELECTRICAL-Rough 6/1/2026 Approved LUIS CASTRO
Final 6/1/2026 Corrections Issued LUIS CASTRO
HVAC-Final 6/1/2026 Approved LUIS CASTRO
HVAC-Rough 6/1/2026 Approved LUIS CASTRO
PLUMBING-Final 6/1/2026 Approved LUIS CASTRO
Service/Power Release 6/1/2026 Not Ready for Inspection LUIS CASTRO
Final 6/8/2026 OK to Issue CofO LUIS CASTRO
Service/Power Release 6/8/2026 Approved LUIS CASTRO