1428 3/4 W 59TH ST 90047
Certificate Information: 1428 3/4 W 59TH ST 90047
- Application / Permit
- 23010-10000-03112
- Plan Check / Job No.
- B23LA14211
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1 STORY ADU (all electric)
- Permit Issued
- Issued on 11/6/2023
- Issuing Office
- Current Status
- CofO Issued on 6/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | HERNAN ARREOLA |
| Corrections Issued | 8/13/2023 | HERNAN ARREOLA |
| Quality Review Completed | 8/24/2023 | PETER KIM |
| Plan Check Approved | 10/25/2023 | HERNAN ARREOLA |
| Issued | 11/6/2023 | APPLICANT |
| CofO in Progress | 6/8/2026 | LUIS CASTRO |
| Permit Finaled | 6/18/2026 | DEROLD HAUFF |
| CofO Issued | 6/18/2026 | DEROLD HAUFF |
| Permit Finaled | 6/18/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 10/17/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2023 | CELINA MORENO |
| Sewer availability | Cleared | 10/24/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagra,, Sukhdeep Singh; Lic. No.: C84908 | PO BOX 1836 YUBA CITY, CA 95992 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/31/2024 | Corrections Issued | RONNIE MINDANAO |
| Underground Mechanical | 2/22/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 2/23/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 2/27/2024 | Corrections Issued | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 3/5/2024 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Partial Approval | CRAIG DAVIS |
| Interior/Exterior Lathing | 6/4/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/6/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 9/6/2024 | Corrections Issued | MICHAEL LEWIS |
| Rough-Elec/Plmb/HVAC | 10/9/2024 | Conditional Approval | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 1/15/2025 | Corrections Issued | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 1/15/2025 | No Access for Inspection | BARRY HACHE |
| HVAC-Rough | 1/23/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 3/4/2025 | Partial Approval | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 3/4/2025 | Approved | OSVALDO PARAMO |
| Insulation | 6/5/2025 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 7/15/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 8/19/2025 | Approved | BARRY HACHE |
| Green Building Rough | 8/19/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 10/16/2025 | Approved | ALEX COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Not Ready | BARRY HACHE |
| BUILDING-Rough-Frame | 4/9/2026 | Approved | RAUL BARAJAS |
| Final | 4/9/2026 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/9/2026 | Approved | RAUL BARAJAS |
| Green Building Final | 4/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Not Ready | RAUL BARAJAS |
| Service/Power Release | 4/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 4/9/2026 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 4/9/2026 | Approved | RAUL BARAJAS |
| Final | 4/17/2026 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 4/17/2026 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/17/2026 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 4/17/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 4/17/2026 | Approved | ENRIQUE MIRELES |
| Final | 5/14/2026 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 5/14/2026 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 6/1/2026 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 6/1/2026 | Approved | LUIS CASTRO |
| Final | 6/1/2026 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 6/1/2026 | Approved | LUIS CASTRO |
| HVAC-Rough | 6/1/2026 | Approved | LUIS CASTRO |
| PLUMBING-Final | 6/1/2026 | Approved | LUIS CASTRO |
| Service/Power Release | 6/1/2026 | Not Ready for Inspection | LUIS CASTRO |
| Final | 6/8/2026 | OK to Issue CofO | LUIS CASTRO |
| Service/Power Release | 6/8/2026 | Approved | LUIS CASTRO |