1330 W 220TH ST 90501

Certificate Information: 1330 W 220TH ST 90501

Application / Permit
23010-10000-03075
Plan Check / Job No.
B23LA13967
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) ACCESSORY LIVING QUARTERS TO DETACHED ACCESSORY DWELLING UNIT WITH 10'2" X 12'4" ADDITION TO REAR, 7'1" X 26' ADDITION TO FRONT, AND 5' X 6'6" PORCH ADDITION TO FRONT PER LAMC 12.22 A.33(c) and (d). CONVERSION OF (E) 138 SF UNPERMITTED PORTION OF BUILDING ACCESSORY DWELLING UNIT PER 65852.2(d)(2)
Permit Issued
Issued on 12/5/2024
Issuing Office
Current Status
CofO Issued on 2/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2023 APPLICANT
Assigned to Plan Check Engineer 9/26/2023 OMAR GARNICA
Corrections Issued 9/27/2023 OMAR GARNICA
Applicant returned to address corrections 12/13/2023 ADRIANA LOPEZ
Applicant returned to address corrections 5/22/2024 OMAR GARNICA
Plan Check Approved 11/16/2024 SARKIS HARABEDIAN
Issued 12/5/2024 APPLICANT
CofO in Progress 2/2/2026 EUGENE CASSIDY
Permit Finaled 2/2/2026 ANSON MAGLASANG
CofO Issued 2/2/2026 ANSON MAGLASANG
Permit Finaled 2/2/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 5/3/2024 ERIK BEASLEY
Roof/Waste drainage to street Cleared 5/6/2024 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/1/2024 XOCHITL ARQUIETA
Sewer availability Cleared 11/12/2024 XOCHITL ARQUIETA

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/20/2025 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 9/5/2025 Approved BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 10/16/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 10/16/2025 No Access for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/16/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/3/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 11/3/2025 Approved EUGENE CASSIDY
Green Building Rough 11/3/2025 Approved EUGENE CASSIDY
HVAC-Rough 11/3/2025 Approved EUGENE CASSIDY
Insulation 11/14/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/14/2025 Partial Approval EUGENE CASSIDY
Shower Pan 11/14/2025 Approved EUGENE CASSIDY
Drywall Nailing 11/18/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/21/2025 Approved EUGENE CASSIDY
Underground Mechanical 12/1/2025 Partial Approval EUGENE CASSIDY
Gas Test 12/23/2025 Approved EUGENE CASSIDY
Final 1/23/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 1/23/2026 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/23/2026 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 1/23/2026 Approved EUGENE CASSIDY
ELECTRICAL-Final 1/28/2026 Approved EUGENE CASSIDY
Final 1/28/2026 OK to Issue CofO EUGENE CASSIDY
Green Building Final 1/28/2026 Approved EUGENE CASSIDY
HVAC-Final 1/28/2026 Approved EUGENE CASSIDY
PLUMBING-Final 1/28/2026 Approved EUGENE CASSIDY
Service/Power Release 1/28/2026 Approved EUGENE CASSIDY