1301 S SOTO ST 90023
Certificate Information: 1301 S SOTO ST 90023
- Application / Permit
- 23010-10000-03011
- Plan Check / Job No.
- B23LA13535
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant - Drive Through Fast Food
- Work Description
- ePlan New construction of fast-food restaurant with a single drive-through queuing lane able to accommodate six (6) vehicles, including a surface parking lot , a trash enclosure with alley access, a loading area, designated pedestrian pathways and perimeter landscaping.
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- CofO Issued on 8/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 8/3/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/17/2023 | FARUK SEZER |
| Applicant returned to address corrections | 7/13/2024 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 10/5/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/28/2024 | ARSALAN SHABESTARI |
| Issued | 11/5/2024 | APPLICANT |
| CofO in Progress | 8/4/2025 | LARRY ARNICK |
| Permit Finaled | 8/7/2025 | ERNESTO CORRAL |
| CofO Issued | 8/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 8/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/17/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 8/17/2023 | YINGSHI HUANG |
| ZI | Cleared | 8/17/2023 | YINGSHI HUANG |
| Address approval | Cleared | 8/24/2023 | CHRISTINA BRACO |
| Highway dedication | Cleared | 8/24/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/29/2023 | CHRISTINA BRACO |
| Historic Resource Verification | Cleared | 8/31/2023 | MAX LODER |
| Prkng lot landscape/Water mgmt | Cleared | 9/6/2023 | YINGSHI HUANG |
| Miscellaneous | Cleared | 9/13/2023 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 9/13/2023 | YASMINE BASHIRI |
| Grading Pre-Inspection | Cleared | 10/16/2023 | ROBERT HUGHES |
| Food establishment approval | Cleared | 10/17/2023 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 10/19/2023 | RAMESHBHAIR PATEL |
| Hydrant and Access approval | Cleared | 10/27/2023 | GILBERT URREA |
| Drive Through | Cleared | 11/7/2023 | COLLINS ALLAN |
| Fire Marshal Fire Life Safety | Cleared | 12/7/2023 | RONILO MULAWIN |
| Green Code | Cleared | 3/15/2024 | Lawrence Quirante |
| Low Impact Development (LID) | Cleared | 6/8/2024 | LUIS LUVANO |
| Permit | Cleared | 6/12/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 6/12/2024 | CHRISTINA BRACO |
| DAS Clearance | Cleared | 7/22/2024 | Lawrence Quirante |
| GPI Written Notices | Cleared | 9/19/2024 | ARSALAN SHABESTARI |
Contact Information
| Architect | Liederman,, Jeffrey Steven; Lic. No.: C29534 | 11812 COLONY DRIVE SANTA ANA, CA 92705 |
| Contractor | Cirks Construction Inc; Lic. No.: 763589-B | , |
| Contractor | K D C Construction; Lic. No.: 763589-B | , |
| Engineer | Allen,, Thomas Christopher; Lic. No.: S5460 | 2 VENTURE, SUITE 200 IRVINE, CA 92618 |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/13/2024 | Partial Inspection | LARRY ARNICK |
| Grading Pre-Inspection | 12/3/2024 | Corrections Issued | LARRY ARNICK |
| Grading Pre-Inspection | 12/19/2024 | Not Ready for Inspection | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 12/30/2024 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 12/30/2024 | Not Ready for Inspection | LARRY ARNICK |
| Reinforced Concrete Frame | 12/30/2024 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 1/6/2025 | Conditional Approval | LARRY ARNICK |
| Masonry Wall/Backfill | 1/16/2025 | Not Ready for Inspection | LARRY ARNICK |
| Masonry Wall/Backfill | 1/21/2025 | Not Ready for Inspection | NICK DANERI |
| Masonry Wall/Backfill | 1/23/2025 | Approved | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 1/24/2025 | Approved | LARRY ARNICK |
| Footing/Foundation/Slab | 1/24/2025 | Approved | LARRY ARNICK |
| Grading Pre-Inspection | 1/24/2025 | Approved | LARRY ARNICK |
| Reinforced Concrete Frame | 1/31/2025 | Not Ready for Inspection | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 2/5/2025 | Partial Approval | LARRY ARNICK |
| T-Bar Ceiling | 2/5/2025 | Not Ready for Inspection | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Partial Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 2/11/2025 | Partial Inspection | RONALD JIMENEZ |
| Green Building Rough | 2/24/2025 | Approved | LARRY ARNICK |
| Verify Sprinkler Sign Off | 2/24/2025 | Not Ready for Inspection | LARRY ARNICK |
| Wall Anchors | 2/24/2025 | Approved | LARRY ARNICK |
| Wood Frame | 2/24/2025 | Conditional Approval | LARRY ARNICK |
| Insulation | 2/26/2025 | Approved | LARRY ARNICK |
| Drywall Nailing | 3/4/2025 | Partial Approval | RONALD JIMENEZ |
| Insulation | 3/4/2025 | Partial Approval | RONALD JIMENEZ |
| Light Gage Steel Frame | 3/4/2025 | Partial Approval | RONALD JIMENEZ |
| Reinforced Concrete Frame | 3/6/2025 | Partial Approval | LARRY ARNICK |
| Interior/Exterior Lathing | 3/11/2025 | Not Ready for Inspection | LARRY ARNICK |
| Reinforced Masonry Frame | 3/11/2025 | Not Ready for Inspection | LARRY ARNICK |
| Interior/Exterior Lathing | 3/17/2025 | Approved | LARRY ARNICK |
| T-Bar Ceiling | 3/18/2025 | Not Ready for Inspection | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 4/8/2025 | SGSOV Not Ready | LARRY ARNICK |
| T-Bar Ceiling | 4/8/2025 | Not Ready for Inspection | LARRY ARNICK |
| Special/Order Compliance | 4/9/2025 | Conditional Approval | LARRY ARNICK |
| Deputy Reinf. Concrete | 4/17/2025 | Conditional Approval | LARRY ARNICK |
| T-Bar Ceiling | 4/29/2025 | Not Ready for Inspection | JEFFREY FULTON |
| Pre-Inspection | 4/30/2025 | Not Ready for Inspection | LARRY ARNICK |
| T-Bar Ceiling | 5/27/2025 | Approved | LARRY ARNICK |
| Pre-Inspection | 7/11/2025 | Partial Approval | LARRY ARNICK |
| Final | 7/14/2025 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 7/14/2025 | Approved | LARRY ARNICK |
| Wood Frame | 7/14/2025 | Approved | LARRY ARNICK |
| Final | 7/17/2025 | Not Ready for Inspection | LARRY ARNICK |
| Green Building Final | 7/17/2025 | Approved | LARRY ARNICK |
| Masonry Wall/Backfill | 7/17/2025 | Approved | LARRY ARNICK |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | LARRY ARNICK |
| Smoke Detectors | 7/17/2025 | Approved | LARRY ARNICK |
| Posting Pre-Inspection | 7/24/2025 | Approved | LARRY ARNICK |
| Final | 8/4/2025 | OK to Issue CofO | LARRY ARNICK |