12835 W GREENE AVE 90066

Certificate Information: 12835 W GREENE AVE 90066

Application / Permit
23010-10000-03002
Plan Check / Job No.
B23LA13482
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER HCD APPROVAL.
Permit Issued
Issued on 1/10/2024
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 DANIEL YIP
Corrections Issued 8/3/2023 DANIEL YIP
Applicant returned to address corrections 11/3/2023 DANIEL YIP
Plan Check Approved 12/6/2023 DANIEL YIP
Issued 1/10/2024 APPLICANT
CofO in Progress 5/16/2024 TEMISTOCLES CAAL
Permit Finaled 5/17/2024 DANIEL ORRANTE
CofO Issued 5/17/2024 DANIEL ORRANTE
Permit Finaled 5/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/1/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 9/6/2023 ANTHONY MAINEZ
Sewer availability Cleared 9/6/2023 ANTHONY MAINEZ
Specific Plan Cleared 9/12/2023 PEDRO AYALA
Roof/Waste drainage to street Cleared 11/8/2023 ANTHONY MAINEZ
Construction near power lines Cleared 11/27/2023 RIDWAN HARDY
Construction within easement Cleared 11/27/2023 RIDWAN HARDY

Contact Information

Contractor Abodu Inc; Lic. No.: 1073522-B       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/13/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 3/28/2024 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 3/28/2024 Partial Approval TEMISTOCLES CAAL
Sewer 3/28/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 4/29/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 5/7/2024 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 5/7/2024 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 5/15/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 5/15/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 5/15/2024 Approved TEMISTOCLES CAAL
Final 5/15/2024 OK to Issue CofO TEMISTOCLES CAAL
Footing/Foundation/Slab 5/15/2024 Approved TEMISTOCLES CAAL
Green Building Final 5/15/2024 Approved TEMISTOCLES CAAL
Green Building Rough 5/15/2024 Approved TEMISTOCLES CAAL
HVAC-Final 5/15/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 5/15/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Not Required TEMISTOCLES CAAL
Smoke Detectors 5/15/2024 Approved TEMISTOCLES CAAL