4457-4459 N LOWELL AVE 90032
Certificate Information: 4457-4459 N LOWELL AVE 90032
- Application / Permit
- 23010-10000-02998
- Plan Check / Job No.
- B23LA13479
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) 25'-6" x 9'-6" ATTACHED GARAGE INTO A (N) ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 5/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2023 | ALFRED RAMIREZ |
| Corrections Issued | 8/3/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 9/12/2023 | ALFRED RAMIREZ |
| No Progress | 9/12/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 9/12/2023 | ALFRED RAMIREZ |
| No Progress | 9/15/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 9/15/2023 | ALFRED RAMIREZ |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 5/3/2024 | LILIANA PORTILLO |
| CofO Issued | 5/8/2024 | DEROLD HAUFF |
| Permit Finaled | 5/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2023 | DAVID VO |
| Sewer availability | Cleared | 8/4/2023 | DAVID VO |
| "Q" conditions | Cleared | 8/7/2023 | YINGSHI HUANG |
| ZI | Cleared | 8/7/2023 | YINGSHI HUANG |
| Tenant Habitability Plan | Cleared | 8/8/2023 | RICARDO BOHORQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | CHRISTINA BRACO |
| Disturb/Remove Protected Trees | Cleared | 8/29/2023 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Evangelista,, Gil Viernes; Lic. No.: S2422 | 749 N FEATHERWOOD DR DIAMOND BAR, CA 91765 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/1/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 11/30/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 12/5/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 12/5/2023 | Approved | AMY COLIN |
| HVAC-Rough | 12/5/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 12/5/2023 | Approved | AMY COLIN |
| Wood Frame | 12/5/2023 | Corrections Issued | AMY COLIN |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | AMY COLIN |
| HVAC-Rough | 1/19/2024 | Approved | AMY COLIN |
| Drywall Nailing | 2/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 2/9/2024 | Approved | JOSH MEISTER |
| Footing/Foundation/Slab | 2/16/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/16/2024 | Approved | LILIANA PORTILLO |
| Final | 4/19/2024 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 4/19/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 5/2/2024 | Approved | LILIANA PORTILLO |
| Final | 5/2/2024 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 5/2/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 5/2/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 5/2/2024 | SGSOV Approved | LILIANA PORTILLO |