6645 W COLGATE AVE 90048
Certificate Information: 6645 W COLGATE AVE 90048
- Application / Permit
- 23010-10000-02996
- Plan Check / Job No.
- B23LA13476
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 2-STORY DETACHED ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) SOLAR INSTALLATION REQ'D TO MEET 2.2 KW PER TITLE 24 PRIOR TO COFO
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- CofO Issued on 4/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | VIVIAN LAO |
| Corrections Issued | 8/22/2023 | VIVIAN LAO |
| Quality Review Completed | 8/23/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/26/2023 | VIVIAN LAO |
| Plan Check Approved | 12/5/2023 | VIVIAN LAO |
| Issued | 1/11/2024 | APPLICANT |
| CofO in Progress | 4/23/2026 | WILBER ROSALES |
| Permit Finaled | 4/27/2026 | RICHARD STEINBACH |
| CofO Issued | 4/27/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/27/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2023 | CELINA MORENO |
| Sewer availability | Cleared | 9/20/2023 | CELINA MORENO |
| Construction near power lines | Cleared | 10/23/2023 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/23/2023 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 11/21/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/6/2023 | CELINA MORENO |
Contact Information
| Contractor | M S Elite General Construction Inc; Lic. No.: 660454-B | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Subgrade | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2024 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/14/2024 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/19/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2024 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/14/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 8/14/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 8/14/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 8/27/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 8/27/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 8/27/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Rough | 8/27/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 8/27/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 8/30/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/17/2024 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Rough | 9/17/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 9/20/2024 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 9/25/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 10/1/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/8/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 10/8/2024 | Approved | MEL KHACHATOURIAN |
| Sewer | 1/8/2025 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 1/8/2025 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/14/2025 | Approved | EVAN COOPER |
| Final | 3/14/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 3/14/2025 | Approved | EVAN COOPER |
| HVAC-Final | 3/14/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/14/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 3/14/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 3/14/2025 | Approved | EVAN COOPER |
| Final | 4/9/2026 | Partial Inspection | SCOTT FINNILA |
| Final | 4/22/2026 | OK to Issue CofO | WILBER ROSALES |