1447 W 91ST PL 90047

Certificate Information: 1447 W 91ST PL 90047

Application / Permit
23010-10000-02988
Plan Check / Job No.
B23LA13461
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Conversion portion of (E) garage with addition into an Accessory Dwelling Unit per Ordinance. Remove (194.5 SQFT) portion of (E) garage to create regular shaped structure. All work per WFPP.
Permit Issued
Issued on 12/6/2023
Issuing Office
Current Status
Issued on 12/6/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/1/2023 DANIEL SMILEY
Corrections Issued 8/2/2023 DANIEL SMILEY
Applicant returned to address corrections 9/9/2023 MINA HABILI
Applicant returned to address corrections 9/30/2023 MINA HABILI
Applicant returned to address corrections 10/5/2023 MICHAEL LANZONE
Plan Check Approved 11/16/2023 MINA HABILI
Issued 12/6/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/9/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/11/2023 HUGO LOPEZ
Sewer availability Cleared 8/11/2023 HUGO LOPEZ
Low Impact Development (LID) Cleared 8/30/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 9/3/2023 AHMED AMARRAGY
Construction near power lines Cleared 11/9/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/10/2024 Approved JOSE MACIAS
Underground Mechanical 4/11/2024 Not Ready for Inspection JOSE MACIAS
Excavation/Setback/Form/Re-Bar 5/29/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 5/29/2024 Approved JOSE MACIAS
Special/Order Compliance 5/29/2026 Corrections Issued SCOTT FINNILA
Underground Mechanical 5/29/2026 Approved SCOTT FINNILA