4250 N GREENBUSH AVE 91423

Certificate Information: 4250 N GREENBUSH AVE 91423

Application / Permit
23010-10000-02987
Plan Check / Job No.
B23LA13460
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan New detached 1,167 s.f. ADU (36' x 32.42'). LAMC 12.22 A.33(c) and (d) 1 of 2
Permit Issued
Issued on 7/15/2024
Issuing Office
Current Status
CofO Issued on 3/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 TSE MING HUANG
Corrections Issued 8/1/2023 TSE MING HUANG
Quality Review Completed 8/4/2023 KEVIN MORALES
Applicant returned to address corrections 5/16/2024 TSE MING HUANG
Applicant returned to address corrections 5/20/2024 TSE MING HUANG
Plan Check Approved 7/15/2024 TSE MING HUANG
Issued 7/15/2024 APPLICANT
CofO in Progress 2/11/2026 MISAEL ESPARZA
Permit Finaled 3/6/2026 RUBEN SALAS
CofO Issued 3/6/2026 RUBEN SALAS
Permit Finaled 3/6/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/13/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/14/2023 CARLOS AGUILERA
Sewer availability Cleared 9/14/2023 CARLOS AGUILERA
ZI Cleared 10/5/2023 BRENNEN OBETO
Construction near power lines Cleared 2/2/2024 RIDWAN HARDY
Construction within easement Cleared 2/2/2024 RIDWAN HARDY
Low Impact Development (LID) Cleared 4/2/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/4/2024 CARLOS AGUILERA

Contact Information

Architect Johnstone,, Darin Robert; Lic. No.: NA29689       ,
Contractor Srk Construction Inc; Lic. No.: 1040488-B       ,

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2024 Partial Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 10/16/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 10/16/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 11/14/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/25/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/25/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/26/2024 Corrections Issued MISAEL ESPARZA
Wood Frame 11/26/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Partial Approval MISAEL ESPARZA
Wood Frame 12/17/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Corrections Issued MISAEL ESPARZA
Sewer 2/4/2025 Corrections Issued MISAEL ESPARZA
Wood Frame 2/4/2025 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 2/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Wood Construction 2/11/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval MISAEL ESPARZA
Sewer 2/20/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Rough 3/12/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 3/12/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/12/2025 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 3/19/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 3/19/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 3/19/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 3/19/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 3/19/2025 Corrections Issued MISAEL ESPARZA
Verify Sprinkler Sign Off 3/19/2025 Partial Inspection MISAEL ESPARZA
Insulation 3/25/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 3/25/2025 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 3/27/2025 Approved MISAEL ESPARZA
Insulation 3/27/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/27/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/9/2025 Conditional Approval MISAEL ESPARZA
Green Building Rough 4/9/2025 Approved MISAEL ESPARZA
Insulation 4/9/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 4/9/2025 Approved MISAEL ESPARZA
Drywall Nailing 4/23/2025 Approved MICHAEL CORTEZ
BUILDING-Rough-Frame 2/2/2026 Not Ready for Inspection MISAEL ESPARZA
Final 2/2/2026 Corrections Issued MISAEL ESPARZA
Green Building Final 2/2/2026 Approved MISAEL ESPARZA
Service/Power Release 2/2/2026 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 2/2/2026 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/10/2026 Approved MISAEL ESPARZA
Final 2/10/2026 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 2/10/2026 Approved MISAEL ESPARZA