808 1/2 N HARPER AVE 90046

Certificate Information: 808 1/2 N HARPER AVE 90046

Application / Permit
23010-10000-02973
Plan Check / Job No.
B23LA13375
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplam: New Deatached 1-Story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d), and (g)
Permit Issued
Issued on 10/30/2023
Issuing Office
Current Status
CofO Issued on 2/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2023 APPLICANT
Assigned to Plan Check Engineer 8/4/2023 DAVID CASTILLO
Corrections Issued 8/5/2023 DAVID CASTILLO
Plan Check Approved 10/21/2023 DAVID CASTILLO
Issued 10/30/2023 APPLICANT
CofO in Progress 2/7/2025 JOSE MACIAS
Permit Finaled 2/11/2025 DEROLD HAUFF
CofO Issued 2/11/2025 DEROLD HAUFF
Permit Finaled 2/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/9/2023 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 8/21/2023 ABEL CASILLAS
Sewer availability Cleared 8/21/2023 ABEL CASILLAS
Construction near power lines Cleared 8/30/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 10/19/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/20/2023 CHRISTINA BRACO

Contact Information

Contractor I D B Enterprise Inc; Lic. No.: 1032682-B       ,
Engineer Builoff,, Sergei; Lic. No.: L8099 4004 SCHUYLKILL DR      CALABASAS, CA 91302
Engineer Ramos,, Victor; Lic. No.: C86568 4823 ALMAGUER AVE      GUADALUPE, CA 93434

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/21/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 1/2/2024 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 1/5/2024 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 1/5/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/19/2024 Approved LILIANA PORTILLO
Underground Mechanical 1/19/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 2/28/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 2/28/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 2/28/2024 Conditional Approval AMIR NAZARIAN
Special/Order Compliance 2/28/2024 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 3/11/2024 Approved AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Conditional Approval AMIR NAZARIAN
HVAC-Rough 3/11/2024 Approved AMIR NAZARIAN
PLUMBING-Rough 3/11/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 3/21/2024 Approved AMIR NAZARIAN
Verify Sprinkler Sign Off 3/21/2024 Approved AMIR NAZARIAN
Insulation 3/26/2024 Not Ready for Inspection AMIR NAZARIAN
Interior/Exterior Lathing 3/26/2024 Partial Approval AMIR NAZARIAN
Insulation 3/29/2024 Approved AMIR NAZARIAN
Drywall Nailing 4/3/2024 Approved AMIR NAZARIAN
Final 1/21/2025 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV No Gas JOSE MACIAS
Service/Power Release 1/21/2025 Not Ready for Inspection JOSE MACIAS
Smoke Detectors 1/21/2025 Approved JOSE MACIAS
Final 1/31/2025 OK to Issue CofO JOSE MACIAS
Service/Power Release 1/31/2025 Approved JOSE MACIAS