808 1/2 N HARPER AVE 90046
Certificate Information: 808 1/2 N HARPER AVE 90046
- Application / Permit
- 23010-10000-02973
- Plan Check / Job No.
- B23LA13375
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplam: New Deatached 1-Story ADU per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d), and (g)
- Permit Issued
- Issued on 10/30/2023
- Issuing Office
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | DAVID CASTILLO |
| Corrections Issued | 8/5/2023 | DAVID CASTILLO |
| Plan Check Approved | 10/21/2023 | DAVID CASTILLO |
| Issued | 10/30/2023 | APPLICANT |
| CofO in Progress | 2/7/2025 | JOSE MACIAS |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
| CofO Issued | 2/11/2025 | DEROLD HAUFF |
| Permit Finaled | 2/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2023 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | ABEL CASILLAS |
| Sewer availability | Cleared | 8/21/2023 | ABEL CASILLAS |
| Construction near power lines | Cleared | 8/30/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 10/19/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/20/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | I D B Enterprise Inc; Lic. No.: 1032682-B | , |
| Engineer | Builoff,, Sergei; Lic. No.: L8099 | 4004 SCHUYLKILL DR CALABASAS, CA 91302 |
| Engineer | Ramos,, Victor; Lic. No.: C86568 | 4823 ALMAGUER AVE GUADALUPE, CA 93434 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/21/2023 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/2/2024 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 1/5/2024 | Corrections Issued | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 1/5/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/19/2024 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 1/19/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Rough | 2/28/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 2/28/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 2/28/2024 | Conditional Approval | AMIR NAZARIAN |
| Special/Order Compliance | 2/28/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/11/2024 | Approved | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Conditional Approval | AMIR NAZARIAN |
| HVAC-Rough | 3/11/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 3/11/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 3/21/2024 | Approved | AMIR NAZARIAN |
| Verify Sprinkler Sign Off | 3/21/2024 | Approved | AMIR NAZARIAN |
| Insulation | 3/26/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Interior/Exterior Lathing | 3/26/2024 | Partial Approval | AMIR NAZARIAN |
| Insulation | 3/29/2024 | Approved | AMIR NAZARIAN |
| Drywall Nailing | 4/3/2024 | Approved | AMIR NAZARIAN |
| Final | 1/21/2025 | Corrections Issued | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV No Gas | JOSE MACIAS |
| Service/Power Release | 1/21/2025 | Not Ready for Inspection | JOSE MACIAS |
| Smoke Detectors | 1/21/2025 | Approved | JOSE MACIAS |
| Final | 1/31/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 1/31/2025 | Approved | JOSE MACIAS |