5725 N CANOGA AVE 1-2 91367

Certificate Information: 5725 N CANOGA AVE 1-2 91367

Application / Permit
23010-10000-02962
Plan Check / Job No.
B23LA13254
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
(2) 1 Story ADUs per State Law
Permit Issued
Issued on 6/13/2025
Issuing Office
Valley
Current Status
Issued on 6/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 HERNAN ARREOLA
Corrections Issued 7/31/2023 HERNAN ARREOLA
Quality Review Completed 8/2/2023 PETER KIM
Building Plans Picked Up 8/7/2023 APPLICANT
Plan Check Approved 5/29/2025 HERNAN ARREOLA
Issued 6/13/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/14/2023 JOHN CONNEALLY
Address approval Cleared 10/16/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/23/2023 COLIN LOREDO
Sewer availability Cleared 10/23/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 3/5/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 4/16/2024 EDGAR ALCARAZ
Specific Plan Cleared 4/3/2025 NATHAN ROMINE
Specific Plan Cleared 5/12/2025 SHEILA AHORAIAN

Contact Information

Architect Dorman,, Christopher J; Lic. No.: C28300 229 FLAMINGO ROAD      MILL VALLEY, CA 94941
Contractor Grundco; Lic. No.: 1016287-B 24372 VANOWEN ST STE 205      WEST HILLS, CA 91307
Engineer Billante,, Ryan Dylan; Lic. No.: C58814 4377 SECOND ST      PLEASANTON, CA 94566

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/22/2025 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 10/24/2025 No Access for Inspection DANIEL VARNUM
Footing/Foundation/Slab 11/11/2025 Partial Approval RICKEY JACKSON
Footing/Foundation/Slab 12/16/2025 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 2/9/2026 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 4/10/2026 Approved ROBERT DAVIS
Wood Frame 4/10/2026 Approved ROBERT DAVIS
Insulation 4/14/2026 Approved GREGORY POMISH
Drywall Nailing 4/21/2026 Approved ROBERT DAVIS
Interior/Exterior Lathing 5/28/2026 Approved ROBERT DAVIS
Interior/Exterior Lathing 6/11/2026 Approved ROBERT DAVIS
Footing/Foundation/Slab 7/24/2026 No Result Entered ROBERT DAVIS