4151 N GRIFFITH PARK DR 90027
Certificate Information: 4151 N GRIFFITH PARK DR 90027
- Application / Permit
- 23010-10000-02945
- Plan Check / Job No.
- B23LA13174
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (23) Patio Cover
- Work Description
- EPLAN SUPPLEMENTAL PERMIT 20010-10000-01336 TO ADD (4) NEW 12' X 22' FABRIC SHADE CANOPY
- Permit Issued
- Issued on 9/9/2024
- Issuing Office
- Current Status
- Issued on 9/9/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2023 | RAPHAEL ROSAS |
| Corrections Issued | 8/8/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 8/11/2023 | STEVEN KIM |
| Applicant returned to address corrections | 12/26/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 8/21/2024 | RAPHAEL ROSAS |
| Issued | 9/9/2024 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 10/3/2023 | MICHAEL AYERS |
| Miscellaneous | Cleared | 10/4/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 10/4/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 10/4/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 10/4/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 10/4/2023 | DANIEL CORONADO |
| ZA Case | Cleared | 10/4/2023 | DANIEL CORONADO |
| ZI | Cleared | 10/4/2023 | DANIEL CORONADO |
| City owned building/parcel | Cleared | 10/6/2023 | RAPHAEL ROSAS |
| HPOZ | Cleared | 10/6/2023 | LAMBERT GIESSINGER |
| Historic Resource Verification | Cleared | 10/6/2023 | LAMBERT GIESSINGER |
| Address approval | Cleared | 10/7/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 10/7/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 10/7/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 10/7/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 10/7/2023 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 10/7/2023 | TREVOR QUAN |
| Highway dedication | Cleared | 10/7/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 10/7/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2023 | TREVOR QUAN |
| Watercourse | Cleared | 10/12/2023 | TERRY PHAN |
| Low Impact Development (LID) | Cleared | 10/24/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/1/2023 | TREVOR QUAN |
| GPI Written Notices | Cleared | 11/2/2023 | MANUEL TEJADA |
| Grading Pre-Inspection | Cleared | 11/2/2023 | MANUEL TEJADA |
| DAS Clearance | Cleared | 12/14/2023 | Shangqin Xie |
Contact Information
| Contractor | Shade Structures Inc; Lic. No.: 989458-B | , |
| Contractor | Usa Shade & Fabric Structures; Lic. No.: 989458-B | , |
| Engineer | Bowen,, William Noble; Lic. No.: C32642 | 1937 BEDFORD RD BEDFORD, TX 76021 |
| Engineer | Zajda,, Sarah; Lic. No.: C72308 | 916 TAIT ST OCEANSIDE, CA 92054 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Approved | DAVID BURKHEAD |
| Green Building Final | 11/5/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| Green Building Rough | 11/5/2025 | Approved | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV No Gas | DAVID BURKHEAD |
| Smoke Detectors | 11/5/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| Special/Order Compliance | 11/5/2025 | Partial Approval | SCOTT SOBEL |
| Structural Steel Frame | 11/5/2025 | Partial Inspection | DAVID BURKHEAD |