2765 W FRANCIS AVE 90005

Certificate Information: 2765 W FRANCIS AVE 90005

Application / Permit
23010-10000-02927
Plan Check / Job No.
B23LA13076
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) TWO STORY SFD TO BE REMODELED AND ADDITION TO BECOME A 4 STORY SFD W/ ATTACHED 4 CAR GARAGE. (FRONT BUILDING). NO PARKING REQUIRED PER AB 2097
Permit Issued
Issued on 9/27/2024
Issuing Office
Current Status
CofO Issued on 3/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 SERGIO GUTIERREZ
Corrections Issued 7/24/2023 SERGIO GUTIERREZ
Quality Review Completed 7/26/2023 RODOLFO ARIAS
Applicant returned to address corrections 2/1/2024 SERGIO GUTIERREZ
Applicant returned to address corrections 4/2/2024 SERGIO GUTIERREZ
Plan Check Approved 8/9/2024 SERGIO GUTIERREZ
Issued 9/27/2024 APPLICANT
CofO in Progress 2/20/2026 WILLIAM SIERRA
No Progress 2/23/2026 DEROLD HAUFF
CofO in Progress 2/23/2026 DEROLD HAUFF
Permit Finaled 3/2/2026 DEROLD HAUFF
CofO Issued 3/2/2026 DEROLD HAUFF
Permit Finaled 3/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/28/2023 ERNEST TSE
Address approval Cleared 7/29/2023 TREVOR QUAN
Highway dedication Cleared 7/29/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/14/2023 TREVOR QUAN
Sewer availability Cleared 8/14/2023 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/20/2023 AHMED AMARRAGY
Frnt yard landscape/Water mgmt Cleared 8/21/2023 DAVID URITA
Miscellaneous Cleared 8/21/2023 DAVID URITA
Trees in Parkway Cleared 8/28/2023 ADALBERTO VERA
Construction near power lines Cleared 12/4/2023 RIDWAN HARDY
Hydrant and Access approval Cleared 5/14/2024 JOHN CONNEALLY
Building over 36-ft Cleared 8/9/2024 CALOSHA APPROVED

Contact Information

Contractor Tripalink Builders Llc; Lic. No.: 1118224-B       ,
Engineer Xia,, Ji; Lic. No.: NA7144       ,
Engineer Xia,, Ji; Lic. No.: S7144 260 S LOS ROBLES AVE, STE 100      PASADENA, CA 91101

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/22/2025 Corrections Issued WILLIAM SIERRA
Underground Mechanical 1/27/2025 Approved WILLIAM SIERRA
Deputy Drilled-In Anchors 2/10/2025 Conditional Approval JOSH MEISTER
Deputy Reinf. Concrete 2/11/2025 Conditional Approval WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 2/14/2025 Approved WILLIAM SIERRA
Special/Order Compliance 2/14/2025 Approved WILLIAM SIERRA
Deputy Reinf. Concrete 2/18/2025 Conditional Approval WILLIAM SIERRA
Sewer 2/26/2025 Corrections Issued WILLIAM SIERRA
Sewer 3/3/2025 Approved WILLIAM SIERRA
Deputy Wood Construction 4/1/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Partial Approval WILLIAM SIERRA
Deputy Wood Construction 5/27/2025 Conditional Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 6/23/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 6/30/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 7/1/2025 Partial Approval WILLIAM SIERRA
ELECTRICAL-Rough 7/14/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 7/14/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 7/18/2025 Corrections Issued WILLIAM SIERRA
HVAC-Rough 7/18/2025 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 7/21/2025 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 7/21/2025 Approved WILLIAM SIERRA
Green Building Rough 7/21/2025 Approved WILLIAM SIERRA
Deputy Drilled-In Anchors 7/24/2025 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 7/28/2025 Approved RONNIE MINDANAO
Deputy Wood Construction 7/29/2025 Conditional Approval JOSH MEISTER
Insulation 8/11/2025 Approved ALEX COLIN
Drywall Nailing 8/28/2025 Approved WILLIAM SIERRA
Gas Test 9/22/2025 Approved WILLIAM SIERRA
Underground Mechanical 9/22/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 11/17/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 11/17/2025 Corrections Issued WILLIAM SIERRA
Smoke Detectors 11/17/2025 Approved WILLIAM SIERRA
Interior/Exterior Lathing 11/25/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 12/19/2025 Approved WILLIAM SIERRA
Green Building Final 12/19/2025 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 12/19/2025 Partial Inspection WILLIAM SIERRA
Underground Mechanical 12/30/2025 Approved WILLIAM SIERRA
HVAC-Final 1/12/2026 Approved WILLIAM SIERRA
PLUMBING-Final 1/27/2026 Approved WILLIAM SIERRA
Final 2/6/2026 Corrections Issued WILLIAM SIERRA
Footing/Foundation/Slab 2/6/2026 Approved WILLIAM SIERRA
Green Building Final 2/6/2026 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Approved WILLIAM SIERRA
Final 2/19/2026 OK to Issue CofO WILLIAM SIERRA
Service/Power Release 2/19/2026 Approved WILLIAM SIERRA