2910 S DANALDA DR 90064

Certificate Information: 2910 S DANALDA DR 90064

Application / Permit
23010-10000-02914
Plan Check / Job No.
B23LA12983
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: MAJOR REMODEL AND ADDITION TO 2-STORY SFD OVER (N) BASEMENT WITH 4-CAR GARAGE AND ATTACHED ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
Issued on 3/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 MAHNAZ NOURHASHEMI
Corrections Issued 7/27/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 8/11/2023 TU HUA
Applicant returned to address corrections 2/22/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 5/20/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 5/30/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 2/7/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 2/21/2025 MAHNAZ NOURHASHEMI
Issued 3/10/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/31/2023 DARIN LAM
Grading Pre-Inspection Cleared 7/31/2023 ROBERT HUGHES
Permit Cleared 7/31/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/2/2023 DARIN LAM
Sewer availability Cleared 8/2/2023 DARIN LAM
Hydrant and Access approval Cleared 9/1/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 4/15/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/26/2024 ANDREA SAINT-ANTONIN
GPI Written Notices Cleared 5/30/2024 MAHNAZ NOURHASHEMI
Specific Plan Cleared 8/14/2024 JOSHUA JONES
Trees in Parkway Cleared 11/19/2024 MIGUEL ORNELAS

Contact Information

Contractor Owner-Builder       ,
Engineer Naraghi-Arani,, Kamran; Lic. No.: NA40985       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

METHANE-Rough 6/8/2026   
Footing/Foundation/Slab 6/8/2026   

Inspection Request History

Pre-Inspection 5/20/2025 Approved DANIEL VERA
Sewer 6/4/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 8/11/2025 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 8/11/2025 Partial Inspection ASHLEY THOMPSON
PLUMBING-Rough 8/13/2025 Partial Approval ASHLEY THOMPSON
Deputy Methane Barrier 8/21/2025 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/3/2025 Corrections Issued ASHLEY THOMPSON
METHANE-Barrier 9/3/2025 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 9/3/2025 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 9/9/2025 Partial Approval ASHLEY THOMPSON
METHANE-Barrier 9/9/2025 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 9/9/2025 Corrections Issued ASHLEY THOMPSON
Deputy Reinf. Concrete 9/10/2025 Conditional Approval ASHLEY THOMPSON
Deputy Methane Barrier 9/24/2025 Conditional Approval ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 9/24/2025 Not Ready for Inspection ASHLEY THOMPSON
Footing/Foundation/Slab 9/29/2025 Corrections Issued HERBERT GIRON
METHANE-Barrier 9/29/2025 Partial Approval HERBERT GIRON
Reinforced Concrete Frame 9/29/2025 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 10/1/2025 Partial Approval ASHLEY THOMPSON
METHANE-Barrier 10/1/2025 Partial Approval ASHLEY THOMPSON
Reinforced Concrete Frame 10/1/2025 Partial Approval ASHLEY THOMPSON
Deputy Shotcrete 10/6/2025 Conditional Approval ASHLEY THOMPSON
Deputy Methane Barrier 11/4/2025 Conditional Approval ANDREW NAVE
METHANE-Subgrade 11/4/2025 Partial Approval RUBEN RIVAS
Underground Mechanical 11/4/2025 Partial Approval RUBEN RIVAS
Deputy Methane Barrier 11/13/2025 Conditional Approval ANDREW NAVE
Deputy Methane Barrier 11/14/2025 Conditional Approval ANDREW NAVE
Deputy Methane Barrier 12/12/2025 Conditional Approval ANDREW NAVE
Deputy Methane Barrier 12/15/2025 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 12/16/2025 Approved ASHLEY THOMPSON
METHANE-Barrier 12/16/2025 Approved ASHLEY THOMPSON
METHANE-Subgrade 12/16/2025 Approved ASHLEY THOMPSON
Deputy Reinf. Concrete 12/22/2025 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 3/4/2026 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Corrections Issued ASHLEY THOMPSON
Deputy Wood Construction 4/28/2026 Conditional Approval ASHLEY THOMPSON
Footing/Foundation/Slab 5/22/2026 Partial Approval ASHLEY THOMPSON
METHANE-Subgrade 5/22/2026 Approved ASHLEY THOMPSON
PLUMBING-Rough 5/22/2026 Partial Approval ASHLEY THOMPSON
Special/Order Compliance 5/22/2026 Corrections Issued ASHLEY THOMPSON
Deputy Reinf. Concrete 5/29/2026 Conditional Approval BOBBY KEY
Deputy Methane Barrier 6/5/2026 Conditional Approval BOBBY KEY