6200 S BROADWAY 1-66 90003

Certificate Information: 6200 S BROADWAY 1-66 90003

Application / Permit
23010-10000-02892
Plan Check / Job No.
B23LA12717
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 5 STORY WITH ROOF DECK 66 UNITS TYPE IIB (51 LI , 14 MI, 1 MANAGER UNIT), 12.22.A.25 / AB 1763 / AB 2345 INCENTIVES
Permit Issued
Issued on 4/25/2025
Issuing Office
Metro
Current Status
Issued on 4/25/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 VU NGUYEN
Assigned to Zoning Architect 7/13/2023 JASON BRAVO
Corrections Issued 7/21/2023 VU NGUYEN
Quality Review Completed 7/25/2023 EUGENE BARBEAU
Plan Check Approved 6/7/2024 VU NGUYEN
Issued 4/25/2025 APPLICANT
TCO Issued (Expire Date: 11-30-2026) 6/3/2026 RAFAEL ESPINOZA

Permit Application Clearance Information

Address approval Cleared 8/17/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/17/2023 ADRIAN SANCHEZ
Community Plan Implem. Overlay Cleared 9/14/2023 TINA MIRANDA
Density Bonus Cleared 9/14/2023 JAMES MCCARTHY
Bicycle Parking Cleared 2/15/2024 MARK REYES
Community Plan Implem. Overlay Cleared 2/20/2024 JESSICA OPINION
Low Impact Development (LID) Cleared 3/7/2024 AMMAR ELTAWIL
Hydrant and Access approval Cleared 3/12/2024 MATTHEW CRAIG
Community Plan Implem. Overlay Cleared 3/13/2024 DYNL MIRANDA
Community Plan Implem. Overlay Cleared 3/13/2024 TAIMOUR TANAVOLI
Roof/Waste drainage to street Cleared 3/13/2024 JESSICA OPINION
Green Code Cleared 3/14/2024 VU NGUYEN
Building over 36-ft Cleared 3/27/2024 CALOSHA APPROVED
Historic Resource Verification Cleared 4/16/2024 YASMINE BASHIRI
Miscellaneous Cleared 4/16/2024 YASMINE BASHIRI
Miscellaneous Cleared 4/16/2024 YASMINE BASHIRI
Redevelopment Project Area Cleared 4/16/2024 YASMINE BASHIRI
Sewer availability Cleared 5/2/2024 JESSICA OPINION
Miscellaneous Cleared 5/15/2024 XIAOLIN LI
Miscellaneous Cleared 5/16/2024 FIPE LEILUA
Miscellaneous Cleared 5/16/2024 FIPE LEILUA
Highway dedication Cleared 5/24/2024 JESSICA OPINION
Trees in Parkway Cleared 6/3/2024 ADALBERTO VERA
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Miscellaneous Cleared 6/4/2024 RUBEN VASQUEZ
Opn space landscape/Water mgmt Cleared 6/4/2024 RUBEN VASQUEZ
Specific Plan Cleared 6/4/2024 RUBEN VASQUEZ
Community Plan Implem. Overlay Cleared 4/18/2025 ANACANY HURTADO
DAS Clearance Cleared 4/22/2025 VU NGUYEN
Fire Marshal Fire Life Safety Cleared 4/23/2025 FIRE DEPARTMENT
Zoning Plan Check Cleared 4/25/2025 Rodolfo Arias

Contact Information

Architect , ; Lic. No.: C39728       ,
Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B 1324 ABBOT KINNEY BLVD      VENICE, CA 90291
Engineer Lothrop,, Shawn Duane; Lic. No.: S5627 27369 VIA INDUCTRIA      TEMECULA, CA 92590
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/17/2025 Approved RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 7/11/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/15/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/16/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/17/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/18/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/21/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/23/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/28/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/29/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/30/2025 Conditional Approval JOEY BUCHANAN
Piling/Pier/Caisson 7/30/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 7/31/2025 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 7/31/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 8/1/2025 Conditional Approval JOEY BUCHANAN
Pre-Inspection 8/5/2025 Approved RAFAEL CORTES
Deputy Steel/Welding 8/8/2025 Partial Approval JAMES POWERS
Pre-Inspection 8/8/2025 Partial Approval JAMES POWERS
Structural Steel Frame 8/11/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 8/12/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 8/13/2025 Approved RAFAEL CORTES
Light Gage Steel Frame 8/15/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 8/19/2025 Partial Approval RAFAEL CORTES
Insulation 8/22/2025 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 8/27/2025 Partial Approval RAFAEL CORTES
Structural Steel Frame 9/10/2025 Partial Approval JOEY BUCHANAN
Deputy Other (see comments) 9/12/2025 Conditional Approval RAFAEL ESPINOZA
Special/Order Compliance 9/12/2025 Corrections Issued RAFAEL ESPINOZA
Structural Steel Frame 9/12/2025 Partial Approval RAFAEL ESPINOZA
Structural Steel Frame 9/16/2025 Partial Approval RAFAEL CORTES
Deputy Other (see comments) 9/18/2025 Conditional Approval RAFAEL CORTES
Deputy Steel/Welding 9/18/2025 Conditional Approval RAFAEL CORTES
Light Gage Steel Frame 9/18/2025 Partial Approval RAFAEL CORTES
Pre-Inspection 9/29/2025 Approved RAFAEL CORTES
Structural Steel Frame 9/29/2025 Partial Approval RAFAEL CORTES
Deputy Steel/Welding 10/10/2025 Conditional Approval RAFAEL ESPINOZA
Light Gage Steel Frame 10/10/2025 Partial Approval RAFAEL ESPINOZA
Deputy Steel/Welding 10/14/2025 Conditional Approval RAFAEL CORTES
Insulation 10/14/2025 No Access for Inspection RAFAEL CORTES
Deputy Other (see comments) 10/17/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 10/17/2025 Conditional Approval JOEY BUCHANAN
Drywall Nailing 10/17/2025 Partial Approval JOEY BUCHANAN
Deputy Other (see comments) 10/22/2025 Conditional Approval RAFAEL CORTES
Deputy Steel/Welding 10/22/2025 Conditional Approval RAFAEL CORTES
Non Compliance 10/22/2025 Not Required RAFAEL CORTES
Pre-Inspection 10/22/2025 Approved RAFAEL CORTES
Deputy Other (see comments) 10/23/2025 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 10/23/2025 Conditional Approval JOEY BUCHANAN
Insulation 10/23/2025 Partial Approval JOEY BUCHANAN
Pre-Inspection 10/27/2025 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 10/28/2025 Partial Approval RAFAEL CORTES
Drywall Nailing 11/3/2025 Partial Approval LARRY ARNICK
Insulation 11/3/2025 Partial Approval LARRY ARNICK
Structural Steel Frame 11/3/2025 Not Ready for Inspection LARRY ARNICK
Wall Anchors 11/3/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 11/4/2025 Partial Approval RAFAEL CORTES
Wall Anchors 11/4/2025 Not Ready for Inspection RAFAEL CORTES
Deputy Other (see comments) 11/7/2025 Partial Approval JAMES POWERS
Drywall Nailing 11/7/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/7/2025 Partial Approval JAMES POWERS
Structural Steel Frame 11/7/2025 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 11/12/2025 Not Ready for Inspection RAFAEL CORTES
Structural Steel Frame 11/12/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 11/14/2025 No Access for Inspection RAFAEL CORTES
Insulation 11/25/2025 Partial Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 11/25/2025 Partial Approval RAFAEL ESPINOZA
Deputy Other (see comments) 11/26/2025 Partial Approval JAMES POWERS
Insulation 11/26/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 11/26/2025 Partial Approval JAMES POWERS
Insulation 12/1/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 12/1/2025 Partial Approval RAFAEL CORTES
Structural Steel Frame 12/1/2025 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Partial Approval RAFAEL CORTES
Insulation 12/2/2025 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 12/3/2025 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Not Ready for Inspection RAFAEL CORTES
Insulation 12/3/2025 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 12/3/2025 Partial Approval RAFAEL CORTES
Deputy Other (see comments) 12/5/2025 Conditional Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 12/5/2025 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 12/5/2025 Partial Approval RAFAEL CORTES
Insulation 12/8/2025 Partial Approval JOEY BUCHANAN
Insulation 12/10/2025 Partial Approval RAFAEL CORTES
Deputy Other (see comments) 12/11/2025 Conditional Approval JOEY BUCHANAN
Drywall Nailing 12/11/2025 Partial Approval JOEY BUCHANAN
Deputy Other (see comments) 12/15/2025 Partial Approval ALFREDO LOPEZ
Drywall Nailing 12/15/2025 Partial Approval ALFREDO LOPEZ
Insulation 12/16/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 12/17/2025 No Access for Inspection RAFAEL CORTES
Insulation 12/18/2025 Partial Approval RAFAEL CORTES
Deputy Other (see comments) 12/23/2025 Partial Approval JAMES POWERS
Insulation 12/23/2025 Partial Approval JAMES POWERS
Drywall Nailing 12/30/2025 Partial Approval LARRY ARNICK
Drywall Nailing 12/31/2025 Partial Approval JOEY BUCHANAN
Drywall Nailing 1/6/2026 Partial Approval RAFAEL CORTES
Insulation 1/6/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 1/7/2026 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 1/8/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 1/9/2026 Partial Approval RAFAEL ESPINOZA
Insulation 1/9/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 1/9/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 1/12/2026 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 1/13/2026 Not Ready for Inspection RAFAEL ESPINOZA
Light Gage Steel Frame 1/14/2026 Corrections Issued LARRY ARNICK
Drywall Nailing 1/16/2026 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/20/2026 Partial Approval JOEY BUCHANAN
Insulation 1/20/2026 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/20/2026 Partial Approval JOEY BUCHANAN
Drywall Nailing 1/21/2026 Partial Approval ALFREDO LOPEZ
Insulation 1/26/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 1/26/2026 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 1/27/2026 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 1/28/2026 Partial Approval RAFAEL CORTES
Insulation 1/29/2026 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 1/29/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 2/2/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 2/2/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 2/3/2026 Partial Approval RAFAEL CORTES
Insulation 2/5/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 2/6/2026 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 2/9/2026 Partial Approval RAFAEL ESPINOZA
Insulation 2/9/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 2/9/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 2/10/2026 Corrections Issued RAFAEL CORTES
Light Gage Steel Frame 2/11/2026 Partial Approval JOEY BUCHANAN
Drywall Nailing 2/12/2026 Partial Approval JOEY BUCHANAN
Interior/Exterior Lathing 2/13/2026 Partial Approval RAFAEL ESPINOZA
Light Gage Steel Frame 2/17/2026 Partial Inspection RAFAEL CORTES
Light Gage Steel Frame 2/23/2026 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 2/26/2026 Partial Approval JOEY BUCHANAN
Masonry Wall/Backfill 3/11/2026 Partial Approval RAFAEL CORTES
Pre-Inspection 3/18/2026 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 3/19/2026 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 3/23/2026 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 3/26/2026 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 4/1/2026 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 4/1/2026 Not Ready for Inspection RAFAEL CORTES
Pre-Inspection 4/1/2026 Approved RAFAEL CORTES
Deputy Steel/Welding 4/2/2026 Approved JOEY BUCHANAN
Drywall Nailing 4/2/2026 Not Ready for Inspection JOEY BUCHANAN
Deputy Reinf. Concrete 4/6/2026 Conditional Approval JOEY BUCHANAN
Pre-Inspection 4/7/2026 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/8/2026 Partial Approval RAFAEL CORTES
Deputy Steel/Welding 4/9/2026 Conditional Approval RAFAEL CORTES
Reinforced Concrete Frame 4/9/2026 Not Ready for Inspection RAFAEL CORTES
Deputy Reinf. Concrete 4/13/2026 Conditional Approval JOEY BUCHANAN
Deputy Steel/Welding 4/13/2026 Conditional Approval JOEY BUCHANAN
Reinforced Concrete Frame 4/13/2026 Partial Approval JOEY BUCHANAN
Deputy Steel/Welding 4/14/2026 Conditional Approval JOEY BUCHANAN
Reinforced Concrete Frame 4/14/2026 Not Ready for Inspection JOEY BUCHANAN
Interior/Exterior Lathing 4/20/2026 Approved JOEY BUCHANAN
Deputy Drilled-In Anchors 4/23/2026 Partial Approval ALFREDO LOPEZ
Deputy Reinf. Concrete 4/23/2026 Partial Approval ALFREDO LOPEZ
Reinforced Concrete Frame 4/23/2026 Partial Approval ALFREDO LOPEZ
Posting Pre-Inspection 4/27/2026 Approved RAFAEL CORTES
Light Gage Steel Frame 5/5/2026 Partial Approval JOEY BUCHANAN
Light Gage Steel Frame 5/11/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 5/12/2026 Approved JOEY BUCHANAN
Light Gage Steel Frame 5/12/2026 Approved JOEY BUCHANAN
Reinforced Concrete Frame 5/15/2026 Approved JOEY BUCHANAN
Pre-Inspection 5/21/2026 Approved RAFAEL CORTES
Posting Pre-Inspection 5/22/2026 Corrections Issued JOEY BUCHANAN
Final 5/26/2026 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 5/26/2026 Approved JOEY BUCHANAN
Green Building Final 5/26/2026 Approved JOEY BUCHANAN
Green Building Rough 5/26/2026 Approved JOEY BUCHANAN
Reinforced Masonry Frame 5/26/2026 Approved JOEY BUCHANAN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Approved JOEY BUCHANAN
Smoke Detectors 5/26/2026 Approved JOEY BUCHANAN
Verify Sprinkler Sign Off 5/26/2026 Approved JOEY BUCHANAN
Posting Pre-Inspection 5/29/2026 Approved JOEY BUCHANAN
Special/Order Compliance 5/29/2026 Approved JOEY BUCHANAN