8723 W ALDEN DR 90048
Certificate Information: 8723 W ALDEN DR 90048
- Application / Permit
- 23010-10000-02882
- Plan Check / Job No.
- B23LA12664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- ePlan New Pre-Fab Storage Container for Chemical Waste for short term storage & disposal.
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Current Status
- CofO Issued on 4/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | PRANITA SHAH |
| Corrections Issued | 7/26/2023 | PRANITA SHAH |
| Quality Review Completed | 8/10/2023 | MICHAEL PEREZ |
| Applicant returned to address corrections | 10/12/2023 | PRANITA SHAH |
| Plan Check Approved | 2/27/2024 | PRANITA SHAH |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 4/4/2025 | EDWIN GREGORYONA |
| CofO Issued | 4/4/2025 | ERNESTO CORRAL |
| Permit Finaled | 4/4/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 8/5/2023 | Hernan Arreola |
| Roof/Waste drainage to street | Cleared | 9/20/2023 | AMBER CAMPBELL |
| Address approval | Cleared | 9/21/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | AMBER CAMPBELL |
| Sewer availability | Cleared | 9/25/2023 | AMBER CAMPBELL |
| DAS Clearance | Cleared | 10/24/2023 | Hernan Arreola |
| Chemical processes | Cleared | 10/29/2023 | SCAQMD APPROVED |
Contact Information
| Architect | Zakian,, Michael Anthony; Lic. No.: C17405 | 4047 SAN RAFAEL LOS ANGELES, CA 90065 |
| Contractor | Joh Harry H Construction Inc; Lic. No.: 469845-B | , |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/26/2024 | No Access for Inspection | EDWIN GREGORYONA |
| Pre-Inspection | 4/29/2024 | Partial Approval | JACOB MYERS |
| Pre-Inspection | 5/9/2024 | Approved | EDWIN GREGORYONA |
| Deputy Grading | 6/6/2024 | Partial Approval | JACOB MYERS |
| Deputy Reinf. Concrete | 6/6/2024 | Partial Approval | JACOB MYERS |
| Excavation/Setback/Form/Re-Bar | 6/6/2024 | Approved | JACOB MYERS |
| Excavation/Setback/Form/Re-Bar | 6/13/2024 | Approved | JACOB MYERS |
| Final | 3/27/2025 | OK to Issue CofO | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 3/27/2025 | Approved | EDWIN GREGORYONA |
| METHANE-Barrier | 3/27/2025 | Approved | EDWIN GREGORYONA |
| METHANE-Final | 3/27/2025 | Approved | EDWIN GREGORYONA |
| METHANE-Rough | 3/27/2025 | Approved | EDWIN GREGORYONA |
| METHANE-Subgrade | 3/27/2025 | Approved | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 3/27/2025 | Approved | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 3/27/2025 | Approved | EDWIN GREGORYONA |
| Wood Frame | 3/27/2025 | Approved | EDWIN GREGORYONA |