4726 N SALOMA AVE 91403

Certificate Information: 4726 N SALOMA AVE 91403

Application / Permit
23010-10000-02880
Plan Check / Job No.
B23LA12659
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** New Detached Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 12/28/2023
Issuing Office
Current Status
Issued on 12/28/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/11/2023 APPLICANT
Assigned to Plan Check Engineer 7/14/2023 EDWIN ESPIN
Corrections Issued 7/15/2023 EDWIN ESPIN
Applicant returned to address corrections 12/21/2023 AMY GUEVARRA
Plan Check Approved 12/28/2023 AMY GUEVARRA
Issued 12/28/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/17/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/19/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 7/19/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 9/18/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 9/20/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 12/12/2023 TINA MIRANDA

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Ha My Design, Inc; Lic. No.: 999603-B       ,

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/15/2024 Corrections Issued THOMAS FINNILA
Underground Mechanical 2/15/2024 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 2/16/2024 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/27/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 3/13/2024 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Partial Approval THOMAS FINNILA
HVAC-Rough 3/13/2024 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 3/13/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/19/2024 Conditional Approval THOMAS FINNILA
Green Building Rough 3/19/2024 Approved THOMAS FINNILA
HVAC-Rough 3/19/2024 Approved THOMAS FINNILA
MERV13>=Rough 3/19/2024 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 3/19/2024 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/26/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/26/2024 Partial Approval THOMAS FINNILA
Sewer 3/26/2024 Approved THOMAS FINNILA
Insulation 4/5/2024 Corrections Issued THOMAS FINNILA
Shower Pan 4/5/2024 Approved THOMAS FINNILA
Insulation 4/9/2024 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/9/2024 Approved THOMAS FINNILA
Drywall Nailing 4/12/2024 Approved THOMAS FINNILA
Final 7/18/2024 Corrections Issued JACK KARGODORIAN
Final 7/26/2024 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 7/26/2024 Approved JACK KARGODORIAN
Green Building Final 7/26/2024 Approved JACK KARGODORIAN
MERV13>=Final 7/26/2024 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Approved JACK KARGODORIAN
Service/Power Release 7/26/2024 Approved JACK KARGODORIAN
Smoke Detectors 7/26/2024 Approved JACK KARGODORIAN
Final 1/23/2025 Not Ready for Inspection JACK KARGODORIAN