8310 N COLUMBUS AVE 91343
Certificate Information: 8310 N COLUMBUS AVE 91343
- Application / Permit
- 23010-10000-02866
- Plan Check / Job No.
- B23LA12582
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY 24 X 60 STATE APPROVED COMMERCIAL COACHE FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) WITH ATTACHED STORAGE
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | SINA KHOSRAVI |
| Corrections Issued | 7/20/2023 | SINA KHOSRAVI |
| Quality Review Completed | 8/4/2023 | KEN GILL |
| Building Plans Picked Up | 8/17/2023 | APPLICANT |
| Applicant returned to address corrections | 4/11/2024 | SINA KHOSRAVI |
| Plan Check Approved | 4/17/2024 | SINA KHOSRAVI |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 9/25/2024 | VINCENT HANLEY |
| Permit Finaled | 10/31/2024 | DANIEL ORRANTE |
| CofO Issued | 10/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/19/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 12/28/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 3/27/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/28/2024 | WALLIE JONG |
Contact Information
| Architect | Agharokh,, Kayumars; Lic. No.: C13027 | 24544 SUNSHINE DRIVE LAGUNA NIGUEL, CA 92677 |
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/26/2024 | Not Ready for Inspection | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 5/1/2024 | Approved | KIRK SANDERS |
| Structural Steel Frame | 5/9/2024 | Corrections Issued | KIRK SANDERS |
| Structural Steel Frame | 5/14/2024 | Approved | VINCENT HANLEY |
| Special/Order Compliance | 6/26/2024 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 7/8/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 7/8/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Sewer | 7/8/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 7/8/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/29/2024 | Partial Approval | VINCENT HANLEY |
| Final | 8/29/2024 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/29/2024 | Approved | VINCENT HANLEY |
| Green Building Final | 8/29/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/29/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/29/2024 | SGSOV Not Ready | VINCENT HANLEY |
| Service/Power Release | 8/29/2024 | Approved | VINCENT HANLEY |
| Smoke Detectors | 8/29/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 8/29/2024 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/23/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/23/2024 | Approved | VINCENT HANLEY |
| Final | 9/23/2024 | Partial Approval | VINCENT HANLEY |
| HVAC-Final | 9/23/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/23/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 9/23/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 9/25/2024 | OK to Issue CofO | VINCENT HANLEY |