1421 W ROLLAND CURTIS PL 90062
Certificate Information: 1421 W ROLLAND CURTIS PL 90062
- Application / Permit
- 23010-10000-02835
- Plan Check / Job No.
- B23LA12437
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN (N) 1-CAR GARAGE WITH ADU ON SECOND LEVEL. ADU PER LAMC 12.22 A.33 (c) & (d)
- Permit Issued
- Issued on 2/2/2024
- Issuing Office
- Current Status
- CofO Issued on 4/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | ADRIANA LOPEZ |
| Corrections Issued | 7/15/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 7/25/2023 | FARUK SEZER |
| Applicant returned to address corrections | 10/17/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 11/7/2023 | ADRIANA LOPEZ |
| Issued | 2/2/2024 | APPLICANT |
| CofO in Progress | 4/11/2025 | SABAS ALONSO |
| Permit Finaled | 4/13/2025 | DEROLD HAUFF |
| Permit Finaled | 4/13/2025 | DEROLD HAUFF |
| CofO Issued | 4/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/10/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 8/14/2023 | CHRISTINA BRACO |
| Low Impact Development (LID) | Cleared | 9/12/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 9/15/2023 | JESSICA OPINION |
Contact Information
| Architect | Karabachian,, Sevak A; Lic. No.: NA38632 | , |
| Contractor | R&M Builders Inc; Lic. No.: 1077165-B | , |
| Engineer | Arakelyan,, Aram; Lic. No.: NA82796 | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 2/16/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 2/16/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Conditional Approval | SABAS ALONSO |
| Deputy Wood Construction | 2/27/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 3/7/2024 | Approved | SABAS ALONSO |
| Sewer | 3/7/2024 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 3/13/2024 | Conditional Approval | JOSH MEISTER |
| ELECTRICAL-Rough | 3/18/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 3/18/2024 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 3/20/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 3/20/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/30/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/30/2024 | Partial Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 4/30/2024 | Approved | SABAS ALONSO |
| Insulation | 6/4/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/15/2024 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/15/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 10/9/2024 | Approved | SABAS ALONSO |
| Final | 10/9/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 10/9/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/9/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 10/9/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 10/9/2024 | Approved | SABAS ALONSO |
| Final | 11/12/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/12/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 11/12/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 12/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 12/18/2024 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 4/2/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/10/2025 | OK to Issue CofO | SABAS ALONSO |