12925 W FERNDALE AVE 90066

Certificate Information: 12925 W FERNDALE AVE 90066

Application / Permit
23010-10000-02809
Plan Check / Job No.
B23LA10387
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ePLAN: NEW DETACHED 1-STORY 1-CAR GARAGE WITH AN ATTACHED STORAGE.
Permit Issued
Issued on 12/3/2024
Issuing Office
Current Status
Issued on 12/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/5/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 CRYSTEL MAALOUF
Corrections Issued 6/28/2023 KHEDER ALRAZAA
Quality Review Completed 7/7/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/9/2023 CRYSTEL MAALOUF
Applicant returned to address corrections 11/13/2023 CRYSTEL MAALOUF
Plan Check Approved 1/23/2024 CRYSTEL MAALOUF
Issued 12/3/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/17/2023 JASON NG
Grading Pre-Inspection Cleared 7/19/2023 MICHAEL TEMPLE
Miscellaneous Cleared 7/19/2023 AHMED AMARRAGY
Specific Plan Cleared 8/2/2023 JOSHUA JONES
Construction near power lines Cleared 8/21/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 10/4/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/11/2023 ANTHONY MAINEZ
Hydrant and Access approval Cleared 11/6/2023 JOHN CONNEALLY
GPI Written Notices Cleared 11/13/2023 MATTHEW JENKINS

Contact Information

Architect Driscoll,, Christopher; Lic. No.: NA36073       ,
Contractor Bless It Construction Inc; Lic. No.: 1048746-B       ,
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 5/28/2025 Conditional Approval MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 6/6/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 6/6/2025 Approved MICHAEL ALLEN
Structural Steel Frame 6/20/2025 Conditional Approval MICHAEL ALLEN
Deputy Wood Construction 8/6/2025 Conditional Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 10/14/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 10/14/2025 Approved WILBER ROSALES
Green Building Rough 10/14/2025 Approved WILBER ROSALES
HVAC-Rough 10/14/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 10/14/2025 Approved WILBER ROSALES
Insulation 10/23/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 10/30/2025 Approved HERBERT GIRON
Final 3/26/2026 Corrections Issued DAKOTA LOW
Green Building Final 3/26/2026 Not Ready for Inspection DAKOTA LOW
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Not Required DAKOTA LOW
Service/Power Release 3/26/2026 Not Ready for Inspection DAKOTA LOW
Smoke Detectors 3/26/2026 Approved DAKOTA LOW
Final 6/18/2026 Corrections Issued MORRIS JACKSON
Green Building Final 6/18/2026 Approved MORRIS JACKSON
Service/Power Release 6/18/2026 Approved MORRIS JACKSON