442 S CROCKER ST 90013

Certificate Information: 442 S CROCKER ST 90013

Application / Permit
23010-10000-02799
Plan Check / Job No.
B23LA10969
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW MISC BUILDING SERVING EMERGENCY HOMELESS SHELTER
Permit Issued
Issued on 3/8/2024
Issuing Office
Current Status
CofO Issued on 8/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 VU NGUYEN
Corrections Issued 7/5/2023 VU NGUYEN
Quality Review Completed 7/5/2023 EUGENE BARBEAU
Applicant returned to address corrections 10/23/2023 VU NGUYEN
Applicant returned to address corrections 1/30/2024 VU NGUYEN
Applicant returned to address corrections 2/27/2024 VU NGUYEN
Plan Check Approved 3/8/2024 VU NGUYEN
Issued 3/8/2024 APPLICANT
TCO Issued (Expire Date: 07-23-2025) 1/24/2025 RAFAEL ESPINOZA
TCO Issued (Expire Date: 01-19-2026) 7/23/2025 RAFAEL ESPINOZA
CofO in Progress 8/4/2025 RAFAEL CORTES
CofO in Progress 8/7/2025 RAFAEL CORTES
CofO Issued 8/7/2025 ERNESTO CORRAL
Permit Finaled 8/7/2025 ERNESTO CORRAL

Permit Application Clearance Information

Public Housing Cleared 7/31/2023 JORGE ALCANTAR
Address approval Cleared 8/1/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/2/2023 WALLIE JONG
DAS Clearance Cleared 8/21/2023 VU NGUYEN
Highway dedication Cleared 8/23/2023 WALLIE JONG
Miscellaneous Cleared 10/11/2023 NOAH MCCOY
Green Code Cleared 10/12/2023 VU NGUYEN
Low Impact Development (LID) Cleared 3/4/2024 ERNEST TSE
Hydrant and Access approval Cleared 3/7/2024 LAVEON RIDER

Contact Information

Architect Yoo,, Ji-Ho; Lic. No.: C32900 1824 LOS ENCINOS AVE      GLENDALE, CA 91208
Contractor Commercial Coating Company Inc; Lic. No.: 475564-A P O BOX 65557      LOS ANGELES, CA 90065
Engineer Hwang,, Junho; Lic. No.: S5592 2450 W MAIN ST      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2024 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 6/11/2024 Conditional Approval RAFAEL ESPINOZA
METHANE-Barrier 6/11/2024 Approved RAFAEL ESPINOZA
METHANE-Subgrade 6/11/2024 Approved RAFAEL ESPINOZA
Masonry Wall/Backfill 7/1/2024 Partial Approval RAFAEL ESPINOZA
Masonry Wall/Backfill 7/10/2024 Approved RAFAEL ESPINOZA
Wall Anchors 7/10/2024 Approved RAFAEL ESPINOZA
Footing/Foundation/Slab 7/18/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/19/2024 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Not Ready for Inspection JEFFREY FULTON
Wood Frame 8/21/2024 Approved RAFAEL ESPINOZA
Insulation 9/3/2024 Not Ready for Inspection JEFFREY FULTON
Final 1/23/2025 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 1/23/2025 Approved RAFAEL CORTES
Green Building Final 1/23/2025 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 1/23/2025 Approved RAFAEL CORTES
METHANE-Final 1/23/2025 Approved RAFAEL CORTES
METHANE-Rough 1/23/2025 Approved RAFAEL CORTES
Reinforced Masonry Frame 1/23/2025 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved RAFAEL CORTES
Smoke Detectors 1/23/2025 Approved RAFAEL CORTES
Verify Sprinkler Sign Off 1/23/2025 Approved RAFAEL CORTES
Final 1/24/2025 OK for TCO RAFAEL CORTES
Green Building Final 1/24/2025 Not Ready for Inspection RAFAEL CORTES
Special/Order Compliance 6/24/2025 No Access for Inspection RAFAEL CORTES
Special/Order Compliance 6/26/2025 Approved RAFAEL CORTES
Final 8/1/2025 OK to Issue CofO RAFAEL CORTES
Green Building Final 8/1/2025 Approved RAFAEL CORTES