442 S CROCKER ST 90013
Certificate Information: 442 S CROCKER ST 90013
- Application / Permit
- 23010-10000-02798
- Plan Check / Job No.
- B23LA10969
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW BATHROOM SERVING EMERGENCY HOMELESS SHELTER
- Permit Issued
- Issued on 3/8/2024
- Issuing Office
- Current Status
- CofO Issued on 8/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | VU NGUYEN |
| Corrections Issued | 7/5/2023 | VU NGUYEN |
| Quality Review Completed | 7/5/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/23/2023 | VU NGUYEN |
| Applicant returned to address corrections | 1/30/2024 | VU NGUYEN |
| Applicant returned to address corrections | 2/27/2024 | VU NGUYEN |
| Plan Check Approved | 3/8/2024 | VU NGUYEN |
| Issued | 3/8/2024 | APPLICANT |
| TCO Issued (Expire Date: 07-23-2025) | 1/24/2025 | RAFAEL ESPINOZA |
| TCO Issued (Expire Date: 01-19-2026) | 7/23/2025 | RAFAEL ESPINOZA |
| CofO in Progress | 8/4/2025 | RAFAEL CORTES |
| CofO Issued | 8/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 8/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Public Housing | Cleared | 7/31/2023 | JORGE ALCANTAR |
| Address approval | Cleared | 8/1/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | WALLIE JONG |
| Sewer availability | Cleared | 8/2/2023 | WALLIE JONG |
| DAS Clearance | Cleared | 8/21/2023 | VU NGUYEN |
| Highway dedication | Cleared | 8/23/2023 | WALLIE JONG |
| Miscellaneous | Cleared | 10/11/2023 | NOAH MCCOY |
| Green Code | Cleared | 10/12/2023 | VU NGUYEN |
| Low Impact Development (LID) | Cleared | 12/12/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 2/29/2024 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 3/7/2024 | LAVEON RIDER |
Contact Information
| Architect | Yoo,, Ji-Ho; Lic. No.: C32900 | 1824 LOS ENCINOS AVE GLENDALE, CA 91208 |
| Contractor | Commercial Coating Company Inc; Lic. No.: 475564-A | P O BOX 65557 LOS ANGELES, CA 90065 |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/19/2024 | Partial Inspection | NICK DANERI |
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Partial Approval | RAFAEL ESPINOZA |
| Pre-Inspection | 5/31/2024 | Approved | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 6/6/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/6/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Concrete | 6/11/2024 | Conditional Approval | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 7/1/2024 | Partial Approval | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 7/10/2024 | Approved | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 7/18/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 8/5/2024 | Partial Inspection | JEFFREY FULTON |
| METHANE-Barrier | 8/5/2024 | Not Ready for Inspection | JEFFREY FULTON |
| METHANE-Subgrade | 8/5/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Approved | RAFAEL ESPINOZA |
| Insulation | 9/3/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 9/3/2024 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 9/3/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 9/27/2024 | Partial Approval | RAFAEL CORTES |
| Insulation | 9/30/2024 | Approved | RAFAEL CORTES |
| Drywall Nailing | 10/4/2024 | Partial Approval | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 10/4/2024 | Approved | RAFAEL ESPINOZA |
| Interior/Exterior Lathing | 10/9/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 1/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 1/24/2025 | Approved | RAFAEL CORTES |
| Green Building Final | 1/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 1/24/2025 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Barrier | 1/24/2025 | Approved | RAFAEL CORTES |
| METHANE-Final | 1/24/2025 | Approved | RAFAEL CORTES |
| METHANE-Rough | 1/24/2025 | Approved | RAFAEL CORTES |
| METHANE-Subgrade | 1/24/2025 | Approved | RAFAEL CORTES |
| Reinforced Masonry Frame | 1/24/2025 | Partial Approval | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 1/24/2025 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 1/24/2025 | Approved | RAFAEL CORTES |
| Special/Order Compliance | 6/24/2025 | No Access for Inspection | RAFAEL CORTES |
| Special/Order Compliance | 6/26/2025 | Approved | RAFAEL CORTES |
| Final | 8/1/2025 | OK to Issue CofO | RAFAEL CORTES |
| Green Building Final | 8/1/2025 | Approved | RAFAEL CORTES |
| Green Building Rough | 8/1/2025 | Approved | RAFAEL CORTES |
| Reinforced Masonry Frame | 8/1/2025 | Approved | RAFAEL CORTES |