3720 S STEPHEN M WHITE DR 90731

Certificate Information: 3720 S STEPHEN M WHITE DR 90731

Application / Permit
23010-10000-02787
Plan Check / Job No.
B23LA12238
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
ePlan The Aquarium Life Support System (LSS) and Equipment Shed shall replace the existing LSS facility within the campus of the Cabrillo Marine Aquarium. The LSS facility filtrates all of the saltwater serving the four primary exhibit zones within the Aquarium. The project scope includes demolition of the existing Pump House and replacement of all existing LSS equipment. The new equipment will be located under a newly constructed open-air fiberglass reinforced plastic shed to protect the equipment from sun and rain.
Permit Issued
Issued on 11/15/2024
Issuing Office
Metro
Current Status
Issued on 11/15/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/2/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 ARSALAN SHABESTARI
Corrections Issued 8/29/2023 ARSALAN SHABESTARI
Quality Review Completed 9/1/2023 FARUK SEZER
Applicant returned to address corrections 4/10/2024 ARSALAN SHABESTARI
Plan Check Approved 10/14/2024 ARSALAN SHABESTARI
Issued 11/15/2024 APPLICANT

Permit Application Clearance Information

Green Code Cleared 8/25/2023 Lawrence Quirante
City Hist. Cultural Monument Cleared 9/12/2023 LAMBERT GIESSINGER
HPOZ Cleared 9/12/2023 LAMBERT GIESSINGER
Historic monument Cleared 9/12/2023 LAMBERT GIESSINGER
ZA Case Cleared 9/12/2023 RYAN LY
Coastal Zone Cleared 9/13/2023 RYAN LY
Eng Process Fee Ord 176,300 Cleared 5/2/2024 ERIK BEASLEY
Sewer availability Cleared 5/2/2024 ERIK BEASLEY
Flood clearance Cleared 5/9/2024 SAMSON WONG
Low Impact Development (LID) Cleared 8/29/2024 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 9/3/2024 KHAING AYE

Contact Information

Contractor Rudolph & Sletten Inc; Lic. No.: 198069-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/13/2025 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 3/21/2025 Partial Approval JOEY BUCHANAN
Deputy Grading 3/26/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 4/1/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 4/1/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 4/25/2025 Approved JOEY BUCHANAN
Deputy Grading 4/28/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 4/29/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 4/30/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 5/1/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 5/1/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 5/2/2025 Conditional Approval DAVID TSAU
Deputy Grading 5/5/2025 Approved JOEY BUCHANAN
Deputy Grading 5/6/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Grading 5/7/2025 No Access for Inspection MICHAEL PETRUSKO
Deputy Grading 5/8/2025 Conditional Approval DAVID TSAU
Deputy Grading 5/9/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Grading 5/13/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 5/14/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 5/28/2025 Conditional Approval JOEY BUCHANAN
Deputy Reinf. Concrete 5/29/2025 Approved JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 5/29/2025 Approved JOEY BUCHANAN
Footing/Foundation/Slab 5/29/2025 Approved JOEY BUCHANAN
Deputy Reinf. Concrete 5/30/2025 Conditional Approval JOEY BUCHANAN
Deputy Grading 6/2/2025 Partial Approval RICARDO ROBLES
Deputy Grading 6/3/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Grading 6/4/2025 Conditional Approval MICHAEL PETRUSKO
Grading Pre-Inspection 6/5/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 6/12/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 6/17/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 6/18/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 6/23/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 6/25/2025 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 6/26/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 6/30/2025 Conditional Approval MICHAEL PETRUSKO
Excavation/Setback/Form/Re-Bar 6/30/2025 Approved MICHAEL PETRUSKO
Deputy Drilled-In Anchors 7/24/2025 Conditional Approval MICHAEL PETRUSKO
Pre-Inspection 7/24/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 7/25/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 7/28/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 7/30/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 7/31/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 8/1/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 8/25/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 8/25/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 8/27/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 8/28/2025 Conditional Approval RICARDO ROBLES
Deputy Drilled-In Anchors 9/3/2025 Conditional Approval FARHAD DADBIN
Deputy Reinf. Concrete 9/4/2025 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 9/5/2025 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 9/8/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 9/22/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 9/23/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 10/3/2025 Conditional Approval RICARDO ROBLES
Deputy Reinf. Concrete 10/3/2025 Conditional Approval RICARDO ROBLES
Deputy Reinf. Concrete 10/6/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 10/15/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 10/16/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 10/20/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 10/22/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Drilled-In Anchors 11/6/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 11/10/2025 Conditional Approval RICARDO ROBLES
Deputy Drilled-In Anchors 11/12/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 11/14/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 11/18/2025 Conditional Approval MICHAEL PETRUSKO
Deputy Grading 12/1/2025 Conditional Approval MICHAEL PETRUSKO
Final 4/16/2026 Partial Inspection DAVID TSAU
SGSOV-Seismic Gas S/O Valve 4/16/2026 SGSOV No Gas DAVID TSAU
Smoke Detectors 4/16/2026 Approved DAVID TSAU
Verify Sprinkler Sign Off 4/16/2026 Approved DAVID TSAU
Wood Frame 4/16/2026 Approved DAVID TSAU