1929 S SPAULDING AVE 90016
Certificate Information: 1929 S SPAULDING AVE 90016
- Application / Permit
- 23010-10000-02785
- Plan Check / Job No.
- B23LA11855
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (2-STORY)
- Permit Issued
- Issued on 1/30/2025
- Issuing Office
- Current Status
- Issued on 1/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | CARLOS MONTES |
| Corrections Issued | 7/5/2023 | CARLOS MONTES |
| Quality Review Completed | 7/19/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/30/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 5/10/2024 | CARLOS MONTES |
| Plan Check Approved | 5/29/2024 | CARLOS MONTES |
| Issued | 1/30/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2023 | CHRISTINA BRACO |
| Low Impact Development (LID) | Cleared | 12/1/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 12/1/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 12/1/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Rainbox International Restoration Of Hermosa Beach; Lic. No.: 1036823-B | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/17/2025 | Approved | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 6/17/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 6/17/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 6/17/2025 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/20/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 7/10/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 7/10/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 8/6/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 8/6/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 8/6/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 9/29/2025 | Partial Inspection | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 9/29/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 9/29/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Rough | 9/29/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 9/29/2025 | Approved | ARTHUR NEGRETE |
| Verify Sprinkler Sign Off | 9/29/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Wood Frame | 9/29/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 11/3/2025 | Not Ready for Inspection | DEVON JACKSON |
| Interior/Exterior Lathing | 11/5/2025 | Partial Approval | DEVON JACKSON |
| Insulation | 12/16/2025 | Corrections Issued | DEVON JACKSON |
| BUILDING-Rough-Frame | 12/17/2025 | Conditional Approval | DEVON JACKSON |
| Green Building Rough | 12/17/2025 | Approved | DEVON JACKSON |
| Insulation | 12/17/2025 | Approved | DEVON JACKSON |
| Verify Sprinkler Sign Off | 12/17/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 12/30/2025 | Not Ready for Inspection | DEVON JACKSON |
| Shower Pan | 12/30/2025 | Not Ready for Inspection | DEVON JACKSON |
| Drywall Nailing | 12/31/2025 | Approved | ALEX COLIN |
| Shower Pan | 12/31/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 3/12/2026 | Approved | WILLIAM SIERRA |
| Sewer | 3/23/2026 | Approved | JUSTIN HAWLEY |