3719-3721 W EVANS ST 90027

Certificate Information: 3719-3721 W EVANS ST 90027

Application / Permit
23010-10000-02776
Plan Check / Job No.
B23LA12197
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan** Proposed 3-story Type VB Single Family Dwelling & ADU with 2 car attached garage.
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
Issued on 10/9/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/7/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 PRANITA SHAH
Corrections Issued 8/1/2023 PRANITA SHAH
Quality Review Completed 8/17/2023 GARO TELMI
Applicant returned to address corrections 9/21/2023 PRANITA SHAH
Applicant returned to address corrections 10/16/2023 PRANITA SHAH
Applicant returned to address corrections 10/24/2023 PRANITA SHAH
Applicant returned to address corrections 1/4/2024 PRANITA SHAH
Applicant returned to address corrections 2/14/2024 PRANITA SHAH
Applicant returned to address corrections 2/22/2024 PRANITA SHAH
Applicant returned to address corrections 3/1/2024 PRANITA SHAH
Applicant returned to address corrections 6/13/2024 PRANITA SHAH
Applicant returned to address corrections 7/10/2024 PRANITA SHAH
Applicant returned to address corrections 8/14/2024 PRANITA SHAH
Applicant returned to address corrections 8/22/2024 PRANITA SHAH
Applicant returned to address corrections 9/12/2024 PRANITA SHAH
Applicant returned to address corrections 9/18/2024 PRANITA SHAH
Plan Check Approved 10/8/2024 PRANITA SHAH
Issued 10/9/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/5/2023 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 8/8/2023 TERRY PHAN
Sewer availability Cleared 8/8/2023 TERRY PHAN
Certificate of Compliance Cleared 8/14/2023 JAZMIN ROQUE
Miscellaneous Cleared 8/14/2023 JAZMIN ROQUE
Hydrant and Access approval Cleared 10/28/2023 KURT CORRAL
Low Impact Development (LID) Cleared 12/8/2023 MELINEH AGHAKHABIAN
Permit Cleared 12/15/2023 TERRY PHAN
Roof/Waste drainage to street Cleared 12/15/2023 TERRY PHAN
Trees in Parkway Cleared 1/19/2024 ADALBERTO VERA
Work Adjacent to Public Way Cleared 8/15/2024 LARRY LEE
GPI Written Notices Cleared 10/1/2024 PRANITA SHAH
Grading Pre-Inspection Cleared 10/1/2024 PRANITA SHAH

Contact Information

Architect Ko,, Michael Myungsoo; Lic. No.: NA22356       ,
Contractor Owner-Builder       ,
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 1424 ROLLING HILLS DR      FULLERTON, CA 92835
Engineer Xia,, Ji; Lic. No.: S7144 260 S LOS ROBLES AVE, STE 100      PASADENA, CA 91101
Geologist Robles,, Gustavo; Lic. No.: EG2422 981 W. ARROW HIGHWAY #191      SAN DIMAS, CA 91773

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2025 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 5/12/2025 Approved ENRIQUE MIRELES
Green Building Rough 5/15/2025 Not Ready for Inspection ENRIQUE MIRELES
Piling/Pier/Caisson 5/15/2025 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 5/15/2025 Not Ready for Inspection ENRIQUE MIRELES
Pre-Inspection 6/3/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/17/2025 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 6/18/2025 Approved ENRIQUE MIRELES
Underground Mechanical 6/27/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/30/2025 Partial Approval JOSE MACIAS
Deputy Shotcrete 7/1/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/9/2025 Approved ENRIQUE MIRELES
Green Building Rough 7/9/2025 Not Ready for Inspection ENRIQUE MIRELES
Reinforced Concrete Frame 7/9/2025 Partial Approval ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/9/2025 Not Ready for Inspection ENRIQUE MIRELES
Deputy Reinf. Concrete 7/10/2025 Conditional Approval JOSH MEISTER
Excavation/Setback/Form/Re-Bar 7/25/2025 Approved ENRIQUE MIRELES
Green Building Rough 7/25/2025 Not Ready for Inspection ENRIQUE MIRELES
Reinforced Concrete Frame 7/25/2025 Partial Approval ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/25/2025 Not Ready for Inspection ENRIQUE MIRELES
Deputy Reinf. Concrete 7/28/2025 Conditional Approval OSVALDO PARAMO
Deputy Reinf. Concrete 7/28/2025 Conditional Approval REGINA MENDEZ
Floor/Roof Diaphrgm/Shear Wall 9/3/2025 Approved ENRIQUE MIRELES
Deputy Steel/Welding 9/18/2025 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved ENRIQUE MIRELES
Deputy Wood Construction 12/2/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/12/2025 Approved ENRIQUE MIRELES
HVAC-Rough 12/12/2025 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/12/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/17/2025 Corrections Issued ENRIQUE MIRELES
Green Building Rough 12/17/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/17/2025 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 12/17/2025 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 12/22/2025 Approved ENRIQUE MIRELES
Deputy Steel/Welding 12/31/2025 Conditional Approval ALEX COLIN
BUILDING-Rough-Frame 1/12/2026 Corrections Issued ENRIQUE MIRELES
Drywall Nailing 1/12/2026 Approved ENRIQUE MIRELES
Shower Pan 1/26/2026 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 1/27/2026 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/3/2026 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 2/5/2026 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/6/2026 Approved ENRIQUE MIRELES
Underground Mechanical 3/3/2026 Approved ENRIQUE MIRELES